Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
6303 E TANQUE VERDE RD
Apply Date:
08/20/2022
Applicant:
Description:
The Tanque Verde Offices PV system will consist of 198 490W DC modules. Grid-tied inverters will sup

Permit Reviews

Permit Number - T22CM06437
Permit Status: Complete
Permit Description: The Tanque Verde Offices PV system will consist of 198 490W DC modules. Grid-tied inverters will sup
Start Date Submittal Complete Date Status  
08/20/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 09/14/2022 COMPLETED Review Details
09/16/2022 RESUBMITTAL 09/19/2022 COMPLETED Review Details
10/13/2022 REVISION - - 1ST 10/20/2022 ACTIVE Review Details
01/07/2023 COMMERCIAL REVIEW - FULL v.1 02/10/2023 APPROVED Review Details

Conditions

Permit Number - T22CM06437
Permit Status: Complete
Permit Description: The Tanque Verde Offices PV system will consist of 198 490W DC modules. Grid-tied inverters will sup
Date Description Comments
02/10/2023 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
02/10/2023 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM06437
Permit Description: The Tanque Verde Offices PV system will consist of 198 490W DC modules. Grid-tied inverters will sup
Total Completed Inspections - 9
Date Description Inspector Results Comments
11/10/2022 COT - LCBU - Excavation/Rebar/Zoning Passed Approved, okay for concrete placement
11/28/2022 COT - LCEL - Electrical Underground Passed Approved underground from solar structure to equipment, ok to backfill progress areas
01/19/2023 COT - LCBU - Framing Passed
01/19/2023 COT - LCEL - Grounding/Bonding Passed
01/19/2023 COT - LCEL - Outdoor Lighting Passed
01/19/2023 COT - LCEL - Electrical Final Passed Approved, DGC Clearance to TEP is required for the solar meter (tied to meter #151514626)
01/19/2023 COT - LCBU - Building Final Passed Solar canopy
01/19/2023 COT - LCEL - Electrical Intermediate Passed
01/19/2023 BULD - Electrical Clearance Passed Approved, DGC Clearance to TEP is required for the solar meter (tied to meter #151514626)

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
FEE BREAKDOWN 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SPEC SHEETS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
STRUCTURAL CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
FEE BREAKDOWN.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SPEC SHEETS.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW
2023-01-03 SI FORM TANQUE VERDE OFFICE - FINAL-2023-01-03_V1.PDF DOCUMENTS VIEW
REV1 PLAN SET.PDF DOCUMENTS VIEW
REV1 REVISION LETTER.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW