Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
08/19/2022
Applicant:
Christi Swenson
Description:
SFR PULT3519-3 T21-M0048

Outstanding Activity Conditions

Permit Number - T22CM06386
Permit Status: Issued
Permit Description: SFR PULT3519-3 T21-M0048
Total Outstanding Activity Conditions - 4
Date Name
08/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
08/19/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
08/19/2022 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.
08/19/2022 NO FINAL UNTIL THE PUBLIC SEWER G-2020-089/P21WP00061 IS ACCEPTED AND RELEASED BY PCRWRD AND NO FINAL UNTIL THE DOWNSTREAMOFFSITE PUBLIC SEWER FOR PARCEL 4 G-2020-087 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM06386
Permite Description: SFR PULT3519-3 T21-M0048
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - RSEL - Grounding/Bonding N/A Not Ready
10/27/2022 COT - RSPL - Plumbing Final N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T22CM06386
Permit Description: SFR PULT3519-3 T21-M0048
Total Completed Inspections - 22
Date Description Inspector Results Comments
03/02/2023 COT - RSPL - Yard Water Line Passed
03/02/2023 COT - RSPL - Sewer Passed
03/06/2023 COT - RSPL - Rough Soil Passed
03/09/2023 COT - RSEL - Grounding/Bonding Passed 3/9/2023 Approved.
03/09/2023 COT - RSBU - Excavation/Rebar/Zoning Passed 3/9/2023 Approved.
03/09/2023 COT - RSEL - Electrical Underground Passed 3/9/2023 Approved.
03/09/2023 COT - RSBU - Preslab Passed Approved. Okay for concrete
03/22/2023 COT - RSBU - Roof Nailing Passed
03/22/2023 COT - RSBU - Exterior Clips/Sheathing Passed
04/24/2023 COT - RSEL - Construction Power Passed TEP ECO
04/24/2023 RSME - Mechanical Progress Passed
04/25/2023 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed
04/25/2023 COT - LCPL - Plumbing Intermediate Passed
04/25/2023 COT - RSPL - Gas Pressure Test Passed
05/08/2023 COT - HCBU - Interior Shear Bracing Passed
06/29/2023 COT - RSPL - Plumbing Final Passed
07/18/2023 COT - RSME - Mechanical Final Passed
07/18/2023 COT - LCBU - Framing Passed
07/18/2023 ENGR Engineering Final Passed
07/18/2023 COT - RSEL - Outdoor Lighting Passed
07/24/2023 RSBU - Building Final Passed
07/25/2023 COT - RSEL - Electrical Final Passed