Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Address:
925 E MILL ST
Address NEW:
925 E MILL ST
Apply Date:
07/29/2022
Applicant:
Oscar Lopez
Description:
TI: MILLVILLE STUDIOS

Permit Reviews

Permit Number - T22CM05805
Permit Status: Needs resubmittal
Permit Description: TI: MILLVILLE STUDIOS
Start Date Submittal Complete Date Status  
07/29/2022 COMMERCIAL - TI 09/15/2022 COMPLETED Review Details
11/07/2022 COMMERCIAL REVIEW - FULL v.1 12/21/2022 REQUIRES RESUBMIT Review Details
08/03/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 08/05/2026 REQUIRES RESUBMIT Review Details
04/01/2024 COMMERCIAL REVIEW - FULL v.4 04/02/2024 APPROVED Review Details
02/26/2024 COMMERCIAL REVIEW - FULL v.2 02/28/2024 IN REVIEW Review Details
11/17/2025 BUILDING DEFERRED SUBMITTAL REVIEW v.1 11/21/2025 APPROVED Review Details
02/28/2024 COMMERCIAL REVIEW - FULL v.3 03/27/2024 REQUIRES RESUBMIT Review Details
04/02/2024 RESTAMP - COMMERCIAL v.1 04/08/2024 APPROVED Review Details

Conditions

Permit Number - T22CM05805
Permit Status: Needs resubmittal
Permit Description: TI: MILLVILLE STUDIOS
Date Description Comments
08/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
07/29/2022 CONTRACTOR LETTER REQUIRED PRIOR TO FINAL INSPECTIONS
08/22/2022 AIR BALANCE REPORT
04/04/2024 WATER STERILIZATION REPORT IS REQUIRED.
01/17/2024 Do not issue final C of O. Prior to project being finalized applicant must provide documentation of purchase of adjacent parcel 124-13-0070 from ADOT.

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: T22CM05805
Permite Description: TI: MILLVILLE STUDIOS
Total Outstanding Inspections - 4
Last Inspection Date Description Inspector Results Comments
11/18/2025 COT - HCBU - Building Final N/A Partial Pass Partial pass. Okay for level 2 TCO. 11/18/2025
11/18/2025 COT - FCON - Fire - Final N/A Partial Pass Ok for Level 2 TCO.
11/18/2025 COT - LCBU - Building Final N/A Partial Pass Partial pass. Okay for level 2 TCO. 11/18/2025
07/28/2026 SITE - Zoning Final N/A Partial Pass Okay to apply for a level 4 TCO

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: T22CM05805
Permit Description: TI: MILLVILLE STUDIOS
Total Completed Inspections - 11
Date Description Inspector Results Comments
09/18/2024 COT - HCPL - Plumbing Intermediate Passed
09/18/2024 COT - HCPL - Rough Soil Passed
09/18/2024 COT - HCBU - Framing Passed Ok to insulate and cover walls
05/23/2025 COT - HCME - Mechanical Intermediate Passed
06/09/2025 BULD - Electrical Clearance Passed Service to be increased to 400 amps and relocated to East side of,building.
11/17/2025 COT - HCME - Mechanical Final Passed
11/17/2025 COT - HCPL - Plumbing Final Passed
11/17/2025 COT - HCBU - Building Progress Passed
07/24/2026 COT - HCBU - Building Final Passed 7/24/26: BUILDING FINAL APPROVED. PENDING ZONING HOLD. ONCE ZONING HOLD HAS BEEN APPROVED PLEASE BE SURE TO REQUEST AND APPLY FOR CofO ON YOUR PORTAL.
07/24/2026 COT - FCON - Fire - Final Passed
07/24/2026 COT - LCBU - Building Final Passed

Documents

File Name Document Type  
COFO_TEMPORARYCOFO (SSRS).PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
MILLVILLE STUDIOS - TAB REPORT_V1.PDF DOCUMENTS VIEW
MILLVILLE.WATERREPORT-2025-11-17_V1.PDF DOCUMENTS VIEW
CONS-2024.03.29_MILLVILLE STUDIOS_3RD SUBMITTAL_V3.PDF DOCUMENTS VIEW
CONS-2024.03.29_MILLVILLE STUDIOS_3RD SUBMITTAL_V3.PDF DOCUMENTS VIEW
DWS_2022.11.06._MILLVILLE STUDIOS_RESPONSE LETTER_V1.PDF DOCUMENTS VIEW
MILLVILLE STUDIOS PHM RESPONSES_V1.PDF DOCUMENTS VIEW