Permit: T22CM05764
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
6809 E VIA OLMEDA
Address NEW:
6809 E VIA OLMEDA
Apply Date:
07/28/2022
Applicant:
Description:
SFR LE23004 T22-M0055
Outstanding Activity Conditions
Permit Number - T22CM05764
Permit Status: Issued
Permit Description: SFR LE23004 T22-M0055
Total Outstanding Activity Conditions - 5
| Date | Name |
|---|---|
| 07/13/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
| 07/13/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
| 07/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 07/28/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/28/2022 | NO FINAL UNTIL THE PUBLIC OFFSITE SEWERG-2020-058/P21WP00065 FOR PARCEL 3, THE PUBLIC OFFSITE SEWER G-2020-101/P21WP00064 FORPARCEL 4, AND THE PUBLIC SEWER G-2020-090/P21WP00062 FOR PARCEL 5, IS ACCEPTED ANDRELEASED BY PCRWRD |
Conditions
Permit Number - T22CM05764
Permit Status: Issued
Permit Description: SFR LE23004 T22-M0055
| Date | Description | Comments |
|---|---|---|
| 07/28/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM05764
Permite Description: SFR LE23004 T22-M0055
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/28/2023 | COT - RSPL - Sewer | N/A | Re-inspection required | HCS not installed correctly |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05764
Permit Description: SFR LE23004 T22-M0055
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/21/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved} | |
| 09/21/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 09/21/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - Approved. Shading required. } |
|
| 10/13/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 10/13/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 10/12/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 10/14/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/13/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - AP canceled} ; {Activity date: 10/13/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE} ; {Activity date: 10/12/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} | |
| 10/14/2022 | COT - RSBU - Preslab | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/13/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE} ; {Activity date: 10/12/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. AB needs to be compacted due to loose ares} | |
| 10/14/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/13/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE 1. Support the ufer in the trench and isolate the vertical by 2” from any other metal 2. Remove all construction debris from pad} ; {Activity date: 10/12/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready provide 3” of clearance all around rebar footing} ; {Activity date: 10/11/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE Maintain min 3" from rebar to earth on all sides. Maintain min 2" from holddowns and rebar to forms. Cancel all other inspections.} |
|
| 11/21/2022 | COT - RSBU - Roof Nailing | Passed | ||
| 12/01/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | corrections were made | |
| 02/16/2023 | COT - RSEL - Construction Power | Passed | TEP ECO | |
| 03/23/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 03/23/2023 | RSME - Mechanical Progress | Passed | ||
| 03/23/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 03/24/2023 | COT - RSPL - Sewer | Passed | ||
| 03/24/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 04/05/2023 | COT - LCBU - Framing | Passed | ||
| 06/20/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 06/20/2023 | COT - BULD - SWG Clearance | Passed | 6/20/23: SWG clearance, meter only. | |
| 06/29/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 06/29/2023 | ENGR Engineering Final | Passed | ||
| 06/30/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 06/30/2023 | COT - RSEL - Electrical Final | Passed | ||
| 06/30/2023 | RSBU - Building Final | Passed | ||
| 06/30/2023 | COT - RSME - Mechanical Final | Passed |