Permit: T22CM05457
Permit Details
Apply Date:
07/19/2022
Applicant:
Michael Becherer
Description:
TI: Restaurant
Permit Reviews
Permit Number - T22CM05457
Permit Status: Issued
Permit Description: TI: Restaurant
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/19/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/16/2022 | COMPLETED |
04/02/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/02/2024 | APPROVED |
11/05/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/09/2022 | REQUIRES RESUBMIT |
01/24/2023 | COMMERCIAL REVIEW - FULL v.2 | 02/14/2023 | REQUIRES RESUBMIT |
04/18/2023 | COMMERCIAL REVIEW - FULL v.1 | 04/28/2023 | APPROVED |
03/03/2023 | COMMERCIAL REVIEW - FULL v.3 | 03/07/2023 | APPROVED |
03/28/2023 | COMMERCIAL REVIEW - FULL v.1 | 03/29/2023 | APPROVED |
Conditions
Permit Number - T22CM05457
Permit Status: Issued
Permit Description: TI: Restaurant
Date | Description | Comments |
---|---|---|
04/01/2024 | AIR BALANCING REPORT IS REQUIRED. | |
04/01/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM05457
Permite Description: TI: Restaurant
Total Outstanding Inspections - 5
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/10/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | |
07/10/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Not Ready | |
07/10/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Not Ready | |
02/13/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Addressing, sticker above exit door, Fire extinguishers mounted on wall, occupant load sign displayed, Places of Assembly permit. |
03/27/2024 | ENGR Engineering Final | N/A | Partial Pass | This permit is approved for a TCO4 only and will remain as such until all plan revisions are made and approved and installed per. the new approved plans. This is for around the actual building area only and does not include any other site inspections like, basins water harvesting landscape or other site improvements. |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM05457
Permit Description: TI: Restaurant
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/10/2023 | FCON – Fire – Intermediate | Passed | None of the fire finals are ready these dont apply to fire or shouldnt | |
07/10/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | ||
07/10/2023 | COT - HCPL - Plumbing Progress | Passed | ||
07/10/2023 | COT - HCME - Mechanical Progress | Passed | ||
07/10/2023 | COT - HCEL - Electrical Progress | Passed | ||
07/27/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
07/27/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
07/27/2023 | COT - HCPL - Rough Soil | Passed | ||
07/27/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
10/11/2023 | COT - HCME - Kitchen Hood | Passed | Kitchen hood, transition, and ductwork are onsite. Workers will be welding transition and ductwork to hood, wrapping ductwork and installing it above the cook area. All welds have been light tested and passed for transition and ductwork. Okay to proceed with installation of hood. | |
12/11/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
01/23/2024 | COT - FCON - Hood System - Final | Passed | ||
02/13/2024 | COT - HCBU - Building Above Ceiling | Passed | ||
02/13/2024 | COT - HCBU - Building Progress | Passed | ||
02/13/2024 | COT - HCEL - Electrical Above Ceiling | Passed | ||
02/13/2024 | COT - HCME - Mechanical Above Ceiling | Passed | ||
03/26/2024 | COT - FCON - Fire - Final | Passed | ||
03/27/2024 | COT - HCBU - TCO | Passed | ||
03/27/2024 | COT - HCBU - Framing | Passed |