Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM05354
Permit Details
Apply Date:
07/14/2022
Applicant:
Vince Catalano
Description:
TI:Nail Spa
Permit Reviews
Permit Number - T22CM05354
Permit Status: Complete
Permit Description: TI:Nail Spa
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/18/2022 | COMPLETED |
08/24/2022 | RESUBMITTAL | 09/14/2022 | COMPLETED |
06/05/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/09/2023 | APPROVED |
Conditions
Permit Number - T22CM05354
Permit Status: Complete
Permit Description: TI:Nail Spa
Date | Description | Comments |
---|---|---|
09/14/2022 | SPECIAL INSPECTION IS REQUIRED - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
09/14/2022 | SPECIAL INSPECTION IS REQUIRED - AIR BALANCE REPORT REQIORED PRIOR TO FINAL INSPECION. | |
09/14/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM05354
Permite Description: TI:Nail Spa
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/28/2022 | COT - LCEL - Service Upgrade | N/A | Canceled | {Activity date: 09/28/2022; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by VVERA1 - na} |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Progress | N/A | Not Ready | |
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
06/01/2023 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
06/01/2023 | COT - LCBU - Building Final | N/A | Re-inspection required | 6/1/23: waiting on Fire Final, several outlets by sinks are not GFCI protected, type the panel schedules on schedule provided by panel manufacturer,restrooms not ready for inspection. |
06/01/2023 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 6/1/23: waiting on Fire Final, several outlets by sinks are not GFCI protected, type the panel schedules on schedule provided by panel manufacturer,restrooms not ready for inspection. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05354
Permit Description: TI:Nail Spa
Total Completed Inspections - 14
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/28/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - CODE RECN/UNIT #115} | |
09/28/2022 | COT - LCEL - Electrical Reconnect | Passed | {Activity date: 09/28/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap Called TEP at 9:45 Clear rec #115} |
|
10/21/2022 | COT - HCPL - Rough Soil | Passed | ||
12/07/2022 | COT - LCEL - Electrical Above Ceiling | Passed | ||
12/07/2022 | COT - LCEL - Electrical Progress | Passed | ||
06/01/2023 | COT - LCME - Mechanical Final | Passed | ||
06/01/2023 | COT - FCON - Fire - Final | Passed | ||
06/01/2023 | COT - FCON - Sprinkler - Final | Passed | ||
06/01/2023 | COT - LCPL - Backwater Valve | Passed | ||
06/02/2023 | COT - LCPL - Plumbing Final | Passed | Plumbing fixtures are installed and operational. | |
06/02/2023 | COT - LCBU - Building Final | Passed | 6-3-23: Fire final was completed yesterday. GFCI outlets have been installed at sink locations. All electrical panels have typed panel schedules inside. Restrooms are complete and functional. Okay to issue Certificate of Occupancy once all other departments have inspected and approved business. | |
06/02/2023 | COT - LCEL - Electrical Final | Passed | 6-3-23: Fire final was completed yesterday. GFCI outlets have been installed at sink locations. All electrical panels have typed panel schedules inside. Restrooms are complete and functional. | |
06/02/2023 | COT - LCME - Mechanical Above Ceiling | Passed | ||
06/02/2023 | COT - LCME - Mechanical Progress | Passed | A/C equipment is installed and properly functioning. |