Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM05348
Permit Details
Apply Date:
07/14/2022
Applicant:
Andrea Flood
Description:
SFR F40J22 T22-M0022
Permit Reviews
Permit Number - T22CM05348
Permit Status: Complete
Permit Description: SFR F40J22 T22-M0022
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2022 | OTHER | 07/28/2022 | COMPLETED |
07/14/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/20/2023 | APPROVED |
Conditions
Permit Number - T22CM05348
Permit Status: Complete
Permit Description: SFR F40J22 T22-M0022
Date | Description | Comments |
---|---|---|
07/14/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
07/14/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
07/14/2022 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. | |
07/14/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM05348
Permit Description: SFR F40J22 T22-M0022
Total Completed Inspections - 23
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/11/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/11/2022 | COT - RSPL - Sewer | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
08/11/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/11/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
09/06/2022 | COT - RSEL - Grounding/Bonding | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
09/06/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/06/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
09/07/2022 | COT - RSBU - Preslab | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/06/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR} | |
09/07/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP} ; {Activity date: 09/06/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE remove mud/dirt from rebar} | |
01/04/2023 | COT - RSBU - Roof Nailing | Passed | ||
03/20/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
03/20/2023 | COT - LCBU - Framing | Passed | ||
03/27/2023 | COT - RSEL - Construction Power | Passed | TEP ECO | |
03/27/2023 | RSME - Mechanical Progress | Passed | 3/27/24: all corrections made | |
03/27/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
03/27/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
04/26/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
07/13/2023 | COT - RSPL - Plumbing Final | Passed | ||
07/13/2023 | RSBU - Building Final | Passed | ||
07/13/2023 | COT - RSME - Mechanical Final | Passed | ||
07/13/2023 | COT - RSEL - Electrical Final | Passed | ||
07/13/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
07/13/2023 | COT - RSBU - Exterior Clips/Sheathing | Passed | ||
07/13/2023 | ENGR Engineering Final | Passed | ||
07/14/2023 | COT - FCON - Sprinkler - Final | Passed |