Permit: T22CM04955
Permit Details
Apply Date:
06/30/2022
Applicant:
Description:
TI: Peter Piper Express
Permit Reviews
Permit Number - T22CM04955
Permit Status: Issued
Permit Description: TI: Peter Piper Express
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
06/30/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/15/2022 | COMPLETED |
08/23/2022 | RESUBMITTAL | 08/29/2022 | COMPLETED |
09/15/2022 | RESUBMITTAL | 09/15/2022 | COMPLETED |
Conditions
Permit Number - T22CM04955
Permit Status: Issued
Permit Description: TI: Peter Piper Express
Date | Description | Comments |
---|---|---|
08/27/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
08/27/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
09/15/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM04955
Permite Description: TI: Peter Piper Express
Total Outstanding Inspections - 10
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - FCON - Hood System - Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Gas Pressure Test | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Progress | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | Need a current fire alarm inspection report showing no deficiencies. |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | Need Knox box with keys to both the front entrance and security door. Need a current fire sprinkler and fire alarm inspection report showing no deficiencies. |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM04955
Permit Description: TI: Peter Piper Express
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/03/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - APPROVED, okay to cover} | |
10/03/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - APPROVED, for grease and sanitary lines, okay to cover} | |
10/17/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved, okay to drywall areas without plumbing} | |
10/17/2022 | COT - LCBU - Framing | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/10/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial pending plumbing and mechanical intermediates, okay to drywall areas without plumbing} ; {Activity date: 10/03/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - PARTIAL, for 6” demising wall with 2 layers fire wall on 1 side only} | |
10/17/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
10/20/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/03/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR} | |
10/20/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
10/20/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 10/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
11/08/2022 | COT - LCBU - Sustainability | Passed | ||
11/15/2022 | COT - LCBU - Building Final | Passed | ||
11/15/2022 | COT - LCEL - Service Upgrade | Passed | ||
11/15/2022 | COT - LCPL - Plumbing Final | Passed |