Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
2650 E ELVIRA RD 132
Apply Date:
06/24/2022
Applicant:
Description:
INTERIOR TENANT IMPROVEMENT ONLY. ALL SITE CONDITIONS TO REMAIN.

Permit Reviews

Permit Number - T22CM04809
Permit Status: Complete
Permit Description: INTERIOR TENANT IMPROVEMENT ONLY. ALL SITE CONDITIONS TO REMAIN.
Start Date Submittal Complete Date Status  
06/24/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 08/09/2022 COMPLETED Review Details
09/14/2022 RESUBMITTAL 09/27/2022 COMPLETED Review Details
03/07/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/11/2024 APPROVED Review Details
02/04/2023 COMMERCIAL REVIEW - FULL v.1 03/07/2023 REQUIRES RESUBMIT Review Details
03/05/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/05/2024 REQUIRES RESUBMIT Review Details

Conditions

Permit Number - T22CM04809
Permit Status: Complete
Permit Description: INTERIOR TENANT IMPROVEMENT ONLY. ALL SITE CONDITIONS TO REMAIN.
Date Description Comments
09/26/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
09/26/2022 SPECIAL INSPECTION IS REQUIRED - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION.
09/26/2022 SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION.
09/26/2022 SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLERS
09/26/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARM
09/26/2022 SHOP DRAWINGS REQUIRED FOR SIGNAGE
09/27/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04809
Permite Description: INTERIOR TENANT IMPROVEMENT ONLY. ALL SITE CONDITIONS TO REMAIN.
Total Outstanding Inspections - 17
Last Inspection Date Description Inspector Results Comments
07/07/2023 COT - LCME - Mechanical Above Ceiling N/A Canceled
07/07/2023 COT - LCEL - Electrical Above Ceiling N/A Canceled
07/07/2023 COT - LCPL - Plumbing Above Ceiling N/A Canceled
10/26/2022 COT - FCON - Sprinkler - Final N/A Not Ready
10/26/2022 COT - FCON - Alarm - Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
01/12/2023 COT - LCBU - Framing N/A Partial Pass partial for hard lid framing in hallway number 114
07/19/2023 COT - LCBU - Building Above Ceiling N/A Not Ready
03/02/2023 COT - LCEL - Electrical Progress N/A Partial Pass Storage racks in warehouse complete; Ok to install electric equipment.
01/12/2023 COT - HCBU - Interior Shear Bracing N/A Partial Pass room 103 - 124. okay
partial for hard lid in hallway 114.
01/12/2023 COT - LCBU - Building Progress N/A Partial Pass ready for tape on drywall.
10/27/2022 COT - LCEL - Electrical Final N/A Not Ready
10/26/2022 COT - LCEL - Electrical Intermediate N/A Not Ready
10/26/2022 COT - LCME - Mechanical Progress N/A Not Ready
10/27/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
02/21/2024 COT - LCBU - Building Final N/A Partial Pass 2/20/24: Air balance report and water sterilization report required prior to final inspection. Pending fire final
2/20/24: condensate drains must be properly supported and coated for UV protection. Electrical whips must be properly supported off of roof.
2/21/24: pending Air balance report and water sterilization report per permit conditions.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04809
Permit Description: INTERIOR TENANT IMPROVEMENT ONLY. ALL SITE CONDITIONS TO REMAIN.
Total Completed Inspections - 22
Date Description Inspector Results Comments
07/19/2023 COT - LCPL - Plumbing Progress Passed
07/19/2023 COT - LCME - Mechanical Above Ceiling Passed
07/19/2023 COT - LCEL - Electrical Above Ceiling Passed
07/19/2023 COT - LCPL - Plumbing Above Ceiling Passed
11/28/2023 COT - FCON - Sprinkler - Final Passed
02/20/2024 COT - FCON - Alarm - Final Passed
02/20/2024 COT - LCPL - Plumbing Final Passed
02/20/2024 COT - HCBU - Preslab Passed
02/20/2024 COT - LCBU - Framing Passed
02/20/2024 COT - FCON - Fire - Final Passed
02/20/2024 COT - LCBU - Building Above Ceiling Passed
02/20/2024 COT - LCEL - Electrical Progress Passed
02/20/2024 COT - HCBU - Framing Passed
02/20/2024 COT - LCME - Mechanical Intermediate Passed
02/20/2024 COT - HCBU - Interior Shear Bracing Passed
02/20/2024 COT - LCBU - Building Progress Passed
02/20/2024 COT - LCEL - Electrical Final Passed
02/20/2024 COT - LCEL - Electrical Intermediate Passed
02/20/2024 COT - LCME - Mechanical Progress Passed
02/20/2024 COT - LCPL - Plumbing Intermediate Passed
02/21/2024 COT - LCME - Mechanical Final Passed
03/25/2024 COT - HCBU - Building Final Passed 3/25/24: Passed ok for CofO