Permit: T22CM04082
Permit Details
Apply Date:
05/31/2022
Applicant:
Cary Broschat
Description:
PV GROUND MOUNTED SOLAR SYSTEM
Permit Reviews
Permit Number - T22CM04082
Permit Status: Complete
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/31/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/11/2022 | COMPLETED |
08/16/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/29/2022 | COMPLETED |
01/23/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/28/2023 | APPROVED |
05/17/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/19/2023 | APPROVED |
Conditions
Permit Number - T22CM04082
Permit Status: Complete
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
Date | Description | Comments |
---|---|---|
06/16/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
02/22/2023 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04082
Permite Description: PV GROUND MOUNTED SOLAR SYSTEM
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
06/07/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Partial pending electrical (correct fuse installation) and securing gates for access |
06/07/2023 | COT - LCEL - Electrical Final | N/A | Partial Pass | Partial, transformer and all electrical equipment is installed pending correct fuse installation |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04082
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
Total Completed Inspections - 10
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/25/2023 | COT - LCEL - Grounding/Bonding | Passed | grounds at service entrance and transformer | |
02/14/2023 | COT - LCEL - Electrical Underground | Passed | all underground is complete, okay to backfill | |
03/14/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | driven piers | |
04/13/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
04/21/2023 | COT - LCBU - Framing | Passed | ||
04/21/2023 | COT - LCBU - Building Progress | Passed | ||
06/11/2023 | BULD - Electrical Clearance | Passed | 6/7/23 - NR - pending correct fuse installation 6/10/23: Correct fuses installed ready to energize |
|
06/10/2023 | COT - LCBU - Building Final | Passed | 4/21/23 - Partial, pending electrical and reports 6/7/23 - Partial pending electrical (correct fuse installation) and securing gates 6/10/23: Correct fuses installed ready to energize |
|
06/10/2023 | COT - LCEL - Electrical Final | Passed | 6/7/23 - Partial, transformer and all electrical equipment is installed pending correct fuse installation 6/10/23: Correct fuses installed ready to energize |
|
06/10/2023 | Building Inspection - Outside Normal Hours Building Inspection | Passed | 4/21/23 - Partial, pending electrical and reports 6/7/23 - Partial pending electrical (correct fuse installation) 6/10/23: Correct fuses installed ready to energize |