Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM04082
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
4401 S TUCSON ESTATES PW
Address NEW:
4401 S TUCSON ESTATES PW
Apply Date:
05/31/2022
Applicant:
Cary Broschat
Description:
PV GROUND MOUNTED SOLAR SYSTEM
Permit Reviews
Permit Number - T22CM04082
Permit Status: Complete
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/31/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 07/11/2022 | COMPLETED |
| 08/16/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/29/2022 | COMPLETED |
| 01/23/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/28/2023 | APPROVED |
| 05/17/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/19/2023 | APPROVED |
Conditions
Permit Number - T22CM04082
Permit Status: Complete
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
| Date | Description | Comments |
|---|---|---|
| 06/16/2022 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
| 02/22/2023 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM04082
Permite Description: PV GROUND MOUNTED SOLAR SYSTEM
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
| 06/07/2023 | COT - LCBU - Building Final | N/A | Partial Pass | Partial pending electrical (correct fuse installation) and securing gates for access |
| 06/07/2023 | COT - LCEL - Electrical Final | N/A | Partial Pass | Partial, transformer and all electrical equipment is installed pending correct fuse installation |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM04082
Permit Description: PV GROUND MOUNTED SOLAR SYSTEM
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/25/2023 | COT - LCEL - Grounding/Bonding | Passed | grounds at service entrance and transformer | |
| 02/14/2023 | COT - LCEL - Electrical Underground | Passed | all underground is complete, okay to backfill | |
| 03/14/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | driven piers | |
| 04/13/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 04/21/2023 | COT - LCBU - Framing | Passed | ||
| 04/21/2023 | COT - LCBU - Building Progress | Passed | ||
| 06/11/2023 | BULD - Electrical Clearance | Passed | 6/7/23 - NR - pending correct fuse installation 6/10/23: Correct fuses installed ready to energize |
|
| 06/10/2023 | COT - LCBU - Building Final | Passed | 4/21/23 - Partial, pending electrical and reports 6/7/23 - Partial pending electrical (correct fuse installation) and securing gates 6/10/23: Correct fuses installed ready to energize |
|
| 06/10/2023 | COT - LCEL - Electrical Final | Passed | 6/7/23 - Partial, transformer and all electrical equipment is installed pending correct fuse installation 6/10/23: Correct fuses installed ready to energize |
|
| 06/10/2023 | Building Inspection - Outside Normal Hours Building Inspection | Passed | 4/21/23 - Partial, pending electrical and reports 6/7/23 - Partial pending electrical (correct fuse installation) 6/10/23: Correct fuses installed ready to energize |