Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCEL - Electrical Underground |
|
Not Ready |
|
| 01/06/2023 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial for ug from panel #1 to panel #2, okay to backfill progress areas |
| 01/23/2023 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial, continue from panel #2 to the transformer, okay to backfill progress areas |
| 02/14/2023 |
COT - LCEL - Electrical Underground |
|
Passed |
all underground is complete, okay to backfill |
| 11/02/2022 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial for underground conduits from panel boards at solar arrays to about 50’ away from equipment gear, okay to backfill progress areas |
| 12/28/2022 |
COT - LCEL - Electrical Underground |
|
Partial Pass |
Partial - ug conduit to inverters, panel boards and array motors, okay to backfill progress areas |