Permit Details

Status:
Inspections Complete
Type:
Commercial Building
Address NEW:
1990 S CRAYCROFT RD
Apply Date:
05/27/2022
Applicant:
Description:
INSTALLATION OF A 15.2 KW AC, 18.105 KW DCROOF MOUNT PHOTOVOLTAIC SYSTEM

Permit Reviews

Permit Number - T22CM04078
Permit Status: Inspections complete
Permit Description: INSTALLATION OF A 15.2 KW AC, 18.105 KW DCROOF MOUNT PHOTOVOLTAIC SYSTEM
Start Date Submittal Complete Date Status  
05/27/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 06/28/2022 COMPLETED Review Details
06/28/2022 RESUBMITTAL 06/29/2022 COMPLETED Review Details
04/13/2023 COMMERCIAL REVIEW - FULL v.1 04/13/2023 REQUIRES RESUBMIT Review Details
03/06/2024 COMMERCIAL REVIEW - FULL v.1 04/08/2024 REQUIRES RESUBMIT Review Details
04/14/2023 COMMERCIAL REVIEW - FULL v.2 05/10/2023 APPROVED Review Details
05/10/2023 RESTAMP - COMMERCIAL v.1 05/10/2023 APPROVED Review Details
04/10/2024 COMMERCIAL REVIEW - FULL v.2 05/09/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections Complete
Permit Number: T22CM04078
Permite Description: INSTALLATION OF A 15.2 KW AC, 18.105 KW DCROOF MOUNT PHOTOVOLTAIC SYSTEM
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
09/19/2024 COT - HCBU - TCO N/A Not Applicable NA

Completed Inspections

Permit Status: Inspections Complete
Permit Number: T22CM04078
Permit Description: INSTALLATION OF A 15.2 KW AC, 18.105 KW DCROOF MOUNT PHOTOVOLTAIC SYSTEM
Total Completed Inspections - 5
Date Description Inspector Results Comments
08/06/2024 COT - LCBU - Framing Passed
08/06/2024 COT - LCEL - Electrical Intermediate Passed
09/19/2024 COT - LCBU - Building Final Passed
09/19/2024 COT - LCEL - Electrical Final Passed
09/19/2024 BULD - Electrical Clearance Passed Approved - DGC Clearance to TEP is required for the solar meter