Permit Details

Status:
Complete
Type:
Commercial Building
Apply Date:
05/25/2022
Applicant:
Description:
Shell Bldg.

Permit Reviews

Permit Number - T22CM04003
Permit Status: Complete
Permit Description: Shell Bldg.
Start Date Submittal Complete Date Status  
05/25/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 06/28/2022 COMPLETED Review Details
07/01/2022 RESUBMITTAL 08/24/2022 COMPLETED Review Details
09/29/2022 RESUBMITTAL 10/13/2022 COMPLETED Review Details
11/21/2022 COMMERCIAL REVIEW - FULL v.2 12/16/2022 REQUIRES RESUBMIT Review Details
01/27/2023 COMMERCIAL REVIEW - FULL v.3 01/31/2023 APPROVED Review Details
11/09/2022 COMMERCIAL REVIEW - FULL v.1 11/10/2022 REQUIRES RESUBMIT Review Details
12/18/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 12/19/2023 APPROVED Review Details
01/10/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/16/2024 APPROVED Review Details

Conditions

Permit Number - T22CM04003
Permit Status: Complete
Permit Description: Shell Bldg.
Date Description Comments
12/13/2022 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
12/19/2023 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
12/19/2023 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
12/13/2022 This project requires the completion of a Fire Construction Permit PRIOR TO FINALING this permit.
01/12/2024 ISSUED WITH PDEQ CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE PRIVATE SEWER #P22SD00117 IS ISSUED A DISCHARGE AUTHORIZATION BY PDEQ
12/19/2023 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
12/13/2022 Steel Bar joists and joist girder designs must be submitted and approved prior to intermediate inspections.
12/13/2022 Structural steel and steel connections designs must be submitted and approved prior to intermediate inspections.
12/19/2023 Post-Installed Anchor Inspection Report is required.
12/13/2022 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
12/19/2023 SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED.
12/19/2023 SPECIAL INSPECTION FOR steel decking/framing IS REQUIRED
12/19/2023 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
12/13/2022 WATER STERILIZATION REPORT IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM04003
Permite Description: Shell Bldg.
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
10/03/2023 COT - BULD - SWG Clearance N/A Not Applicable
10/03/2023 COT - HCME - Mechanical Above Ceiling N/A Not Applicable
10/03/2023 COT - HCBU - Exterior Clips/Sheathing N/A Not Applicable
10/03/2023 COT - HCME - Mechanical Underground N/A Not Applicable
10/03/2023 COT - HCPL - Plumbing Above Ceiling N/A Not Applicable
09/27/2023 COT - HCEL - Outdoor Lighting N/A Partial Pass 9/27/23: south development 8 light pole bases ok to pour rebar per plan.
09/27/2023 COT - HCEL - Electrical Underground N/A Partial Pass 9/27/23: south development 8 light pole bases ok to pour rebar per plan.
06/16/2023 COT - HCPL - Plumbing Progress N/A Partial Pass 6-16-23: Domestic water inside Building.
11/15/2023 COT - FCON - Fire - Final N/A Partial Pass (2) Exit discharge lights not working, (2) Fire sprinkler leaks east end, Fire extinguisher not mounted to pillar, Fire extinguisher missing, Knox box keys.
04/27/2023 COT - LCBU - Excavation/Rebar/Zoning N/A Partial Pass 4-27-23. Tilt up panels number 44, 46, 50, 51 and 62 thru 77.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM04003
Permit Description: Shell Bldg.
Total Completed Inspections - 29
Date Description Inspector Results Comments
06/02/2023 COT - HCBU - Roof Nailing Passed
06/06/2023 COT - HCEL - Grounding/Bonding Passed
06/26/2023 COT - HCBU - Masonry Pregrout Passed
08/23/2023 COT - HCME - Mechanical Progress Passed
09/19/2023 COT - HCME - Mechanical Final Passed 9/19/23: Exhaust fans passed
10/03/2023 COT - HCBU - Interior Shear Bracing Passed
10/03/2023 COT - HCBU - Building Progress Passed
10/03/2023 COT - HCBU - Framing Passed
10/03/2023 COT - HCPL - Sewer Passed
10/13/2023 BULD - Electrical Clearance Passed Approved for (4) service panels/meters under 1 address, ECO Clearances to TEP are required for meters #100, #200, #HSE, #FPMP
10/19/2023 COT - HCBU - Building Above Ceiling Passed
10/19/2023 COT - HCEL - Electrical Above Ceiling Passed
10/19/2023 COT - HCEL - Electrical Intermediate Passed
10/19/2023 COT - HCEL - Electrical Progress Passed
10/19/2023 COT - HCEL - Outdoor Lighting Passed
10/19/2023 COT - HCME - Mechanical Intermediate Passed
10/19/2023 COT - HCPL - Plumbing Intermediate Passed
10/19/2023 COT - HCPL - Rough Soil Passed
10/19/2023 COT - HCPL - Yard Water Line Passed
10/19/2023 COT - HCEL - Electrical Underground Passed
10/19/2023 COT - HCPL - Plumbing Progress Passed
11/21/2023 COT - FCON - Fire - Final Passed
12/04/2023 COT - LCBU - Excavation/Rebar/Zoning Passed
12/04/2023 COT - HCBU - Building Final Passed 12/4/23: building final for shell only.
12/04/2023 COT - HCBU - Preslab Passed
12/04/2023 COT - HCPL - Backwater Valve Passed
12/04/2023 COT - HCEL - Electrical Final Passed
12/04/2023 COT - HCPL - Plumbing Final Passed
12/14/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
BLDG 2 - 3 STERILIZATION REPORT-2024-01-09_V1.PDF DOCUMENTS VIEW
EQ SEWER DA_V1.PDF DOCUMENTS VIEW
CITY OF TUCSON SI CERTS T22CM04003 - BUILDING 3-2023-12-18_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
SUB 5 TUCSON COMMERCE CENTER BUILDING 3 PLAN SET 2022-11-10 T22CM04003_V1.PDF DOCUMENTS VIEW