Permit: T22CM03993
Permit Details
Apply Date:
05/25/2022
Applicant:
Description:
TI: CIRCLE K
Permit Reviews
Permit Number - T22CM03993
Permit Status: Expired
Permit Description: TI: CIRCLE K
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/25/2022 | COMMERCIAL - TI | 06/21/2022 | COMPLETED |
| 05/20/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/21/2024 | REQUIRES RESUBMIT |
| 11/14/2022 | COMMERCIAL REVIEW - FULL v.1 | 12/27/2022 | REQUIRES RESUBMIT |
| 01/24/2023 | COMMERCIAL REVIEW - FULL v.2 | 03/01/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM03993
Permit Status: Expired
Permit Description: TI: CIRCLE K
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 05/03/2024 | AIR BALANCING REPORT IS REQUIRED. |
| 05/03/2024 | COUNTY HEALTH INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. |
Outstanding Inspections
Permit Status: Expired
Permit Number: T22CM03993
Permite Description: TI: CIRCLE K
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/13/2022 | COT - LCME - Mechanical Final | N/A | Re-inspection required | {Activity date: 06/13/2022; Status: Prior to Final Inspectn; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - AIR BALANCE REPORT REQUIRED (EXHAUST ONLY)} |
| 09/07/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Not Applicable | |
| 09/07/2023 | COT - BULD - SWG Clearance | N/A | Not Applicable | |
| 10/12/2023 | COT - HCME - Mechanical Intermediate | N/A | Not Applicable | |
| 10/12/2023 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 10/12/23: remove all boxes/containers in front of electric panels. Waiting on Site Engineering and Fire finals. |
Completed Inspections
Permit Status: Expired
Permit Number: T22CM03993
Permit Description: TI: CIRCLE K
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/31/2023 | COT - HCPL - Rough Soil | Passed | 8/31/23: 3 new floor sinks and 1 new mop sink approved to cover | |
| 09/06/2023 | BULD - Electrical Clearance | Passed | Approved 3 Phase Service upgrade, INCR Clearance was called into TEP at 10:30am (powerkill) | |
| 09/08/2023 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 10/12/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
| 10/12/2023 | COT - FCON - Fire - Final | Passed | ||
| 11/14/2023 | COT - HCME - Mechanical Final | Passed | ||
| 11/14/2023 | SITE - Zoning Final | Passed | ||
| 11/16/2023 | COT - HCPL - Plumbing Final | Passed | ||
| 11/16/2023 | COT - LCEL - Electrical Final | Passed | ||
| 11/16/2023 | COT - LCBU - Building Final | Passed |