Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
1255 S BEVERLY AV
Apply Date:
05/18/2022
Applicant:
garrett Murphy
Description:
180kW AC Photovoltaic Shade Structure Installation

Permit Reviews

Permit Number - T22CM03812
Permit Status: Complete
Permit Description: 180kW AC Photovoltaic Shade Structure Installation
Start Date Submittal Complete Date Status  
05/18/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 06/28/2022 COMPLETED Review Details
10/20/2022 RESUBMITTAL 10/20/2022 COMPLETED Review Details
03/21/2023 COMMERCIAL REVIEW - FULL v.1 04/06/2023 APPROVED Review Details

Conditions

Permit Number - T22CM03812
Permit Status: Complete
Permit Description: 180kW AC Photovoltaic Shade Structure Installation
Date Description Comments
06/06/2022 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
06/06/2022 SPECIAL INSPECTION FOR SPECIAL MOMENT RESISTING STEEL FRAMES IS REQUIRED.
06/06/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
06/06/2022 SPECIAL INSPECTION FOR PILING, DRILLED PIERS AND CAISSONS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM03812
Permite Description: 180kW AC Photovoltaic Shade Structure Installation
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Framing N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM03812
Permit Description: 180kW AC Photovoltaic Shade Structure Installation
Total Completed Inspections - 11
Date Description Inspector Results Comments
12/20/2022 COT - LCBU - Excavation/Rebar/Zoning Passed Approved, okay for concrete placement
12/20/2022 COT - LCEL - Grounding/Bonding Passed 15’ column depth
12/27/2022 COT - LCEL - Electrical Underground Passed Approved Pump 1, okay for backfill and concrete placement
01/26/2023 COT - LCBU - Framing Passed
01/26/2023 COT - LCBU - Building Progress Passed
02/09/2023 COT - LCEL - Electrical Intermediate Passed
02/09/2023 COT - LCEL - Outdoor Lighting Passed
03/27/2023 COT - LCEL - Electrical Final Passed
03/27/2023 COT - LCBU - Building Final Passed
03/27/2023 BULD - Electrical Clearance Passed
06/01/2023 COT - LCEL - Electrical Progress Passed

Documents

File Name Document Type  
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
T22CM03812 - COT 1255 BEVERLY - SI CERTIFICATE-2023-03-21_V1.PDF DOCUMENTS VIEW
T22CM03812 - COT 1255 BEVERLY - SI FINAL REPORT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT.PDF DOCUMENTS VIEW
PLANS.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
STRUCTURAL CALCS.PDF DOCUMENTS VIEW