Permit: T22CM03715
Permit Details
Apply Date:
05/16/2022
Applicant:
Description:
TI: new marijuana cultivation
Permit Reviews
Permit Number - T22CM03715
Permit Status: Complete
Permit Description: TI: new marijuana cultivation
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/16/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 06/28/2022 | COMPLETED |
08/16/2022 | RESUBMITTAL | 09/08/2022 | COMPLETED |
09/21/2022 | RESUBMITTAL | 09/26/2022 | COMPLETED |
10/03/2022 | RESUBMITTAL | 10/13/2022 | COMPLETED |
02/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/22/2024 | REQUIRES RESUBMIT |
06/22/2023 | COMMERCIAL REVIEW - FULL v.1 | 06/27/2023 | REQUIRES RESUBMIT |
01/30/2024 | COMMERCIAL REVIEW - FULL v.2 | 01/30/2024 | APPROVED |
02/01/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/01/2024 | APPROVED |
03/27/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/28/2024 | APPROVED |
09/14/2023 | COMMERCIAL REVIEW - FULL v.2 | 09/22/2023 | APPROVED |
11/15/2023 | COMMERCIAL REVIEW - FULL v.1 | 12/15/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM03715
Permit Status: Complete
Permit Description: TI: new marijuana cultivation
Date | Description | Comments |
---|---|---|
10/12/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
10/12/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
10/12/2022 | SHOP DRAWINGS REQUIRED FOR FIRE SPRINKLER SYSTEM. | |
10/12/2022 | SHOP DRAWINGS REQUIRED FOR FIRE ALARM SYSTEM. | |
10/12/2022 | SHOP DRAWINGS REQUIRED FOR SIGNAGE. | |
10/12/2022 | SHOP DRAWINGS REQUIRED FOR GAS DETECTION ALARM (CO2 SYSTEM). |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03715
Permite Description: TI: new marijuana cultivation
Total Outstanding Inspections - 18
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
09/15/2023 | COT - LCME - Mechanical Progress | N/A | Partial Pass | Grow rooms and processing room on South side, except for west end. |
09/27/2023 | COT - LCBU - Framing | N/A | Re-inspection required | Interior walls and demising wall is properly framed. Ceilings in small grow rooms are framed. Hallway is not framed waiting for final approval on whether it will be a hard lid or drop ceiling. 9/27/23: No plans provided for inspection |
09/15/2023 | COT - LCBU - Building Above Ceiling | N/A | Partial Pass | Grow rooms and processing room on South side, except for west end. |
09/27/2023 | COT - LCEL - Electrical Progress | N/A | Re-inspection required | Grow rooms and processing room on South side, except for west end. 9/27/23: No plans provided for inspection |
09/27/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Re-inspection required | Grow rooms and processing room on South side, except for west end. 9/27/23: No plans provided for inspection |
09/27/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Re-inspection required | Grow rooms and processing room on South side, except for west end. 9/27/23: No plans provided for inspection |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
09/15/2023 | COT - LCME - Mechanical Intermediate | N/A | Partial Pass | Grow rooms and processing room on South side, except for west end. |
06/29/2023 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
09/27/2023 | COT - LCPL - Plumbing Progress | N/A | Re-inspection required | Grow rooms and processing room on South side, except for west end. 9/27/23: No plans provided for inspection |
09/15/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Partial Pass | Grow rooms and processing room on South side, except for west end. |
02/01/2024 | COT - LCBU - Masonry Pregrout | N/A | Not Applicable | |
02/01/2024 | COT - LCBU - Preslab | N/A | Not Applicable | |
02/01/2024 | COT - LCEL - Temporary Service | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03715
Permit Description: TI: new marijuana cultivation
Total Completed Inspections - 22
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/03/2023 | COT - LCPL - Plumbing Intermediate | Passed | Plumbing rough-in is complete. Okay to insulate and sheet rock walls. | |
05/03/2023 | COT - LCEL - Electrical Intermediate | Passed | Electrical rough-in is complete. Okay to insulate and sheet rock walls. | |
11/27/2023 | BULD - Electrical Clearance | Passed | Approved 600A service panel upgrade, INCR Clearance to TEP is required for unit #107 (the cutover) 12/4/23 TEP requesting meter # |
|
11/27/2023 | COT - LCEL - Service Upgrade | Passed | Approved 600A service panel upgrade, INCR Clearance to TEP is required for unit #107 (the cutover) | |
01/18/2024 | COT - ENGR - Site - Assurance Release | Passed | ||
01/22/2024 | COT - LCME - Mechanical Progress | Passed | ||
01/22/2024 | COT - LCBU - Framing | Passed | ||
01/22/2024 | COT - LCBU - Building Above Ceiling | Passed | ||
01/22/2024 | COT - LCEL - Electrical Progress | Passed | ||
01/22/2024 | COT - FCON - Sprinkler - Final | Passed | ||
01/24/2024 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
01/24/2024 | COT - LCEL - Electrical Above Ceiling | Passed | ||
01/24/2024 | COT - HCBU - Interior Shear Bracing | Passed | ||
02/01/2024 | COT - LCPL - Plumbing Final | Passed | ||
02/01/2024 | COT - LCME - Mechanical Final | Passed | ||
02/01/2024 | COT - FCON - Fire - Final | Passed | ||
02/01/2024 | COT - LCME - Mechanical Intermediate | Passed | ||
02/01/2024 | COT - LCEL - Electrical Underground | Passed | ||
02/01/2024 | COT - LCPL - Plumbing Progress | Passed | ||
02/01/2024 | COT - LCME - Mechanical Above Ceiling | Passed | ||
02/01/2024 | COT - LCEL - Electrical Final | Passed | ||
02/13/2024 | COT - LCBU - Building Final | Passed |