Permit: T22CM03486
Permit Details
Status:
Issued
Type:
Commercial Building
Address:
1970 W VALENCIA RD
Address NEW:
1970 W VALENCIA RD
Apply Date:
05/06/2022
Applicant:
Bruce VanBuskirk
Description:
Provide 5 new panels for new gate power around complex
Permit Reviews
Permit Number - T22CM03486
Permit Status: Issued
Permit Description: Provide 5 new panels for new gate power around complex
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/06/2022 | OTHER | 06/02/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM03486
Permite Description: Provide 5 new panels for new gate power around complex
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCEL - Electrical Intermediate | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM03486
Permit Description: Provide 5 new panels for new gate power around complex
Total Completed Inspections - 6
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Approved from panel to gates, okay to backfill} | |
| 06/22/2022 | BULD - Electrical Clearance | Passed | {Activity date: 06/22/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - CODE ECO/ PANELS FOR BUILDINGS 3, 5, 9, 21.} | |
| 07/27/2022 | COT - LCEL - Service Upgrade | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved for the transformer panel designated for building #13, please send ECO Clearance to TEP (Note: this completes all 5 panels and clearances for this permit) } ; {Activity date: 07/19/2022; Status: Correction Required; Inspector: SCARRAZCO; Comment: Entered by NGARCIA3 - corrections required. Expose ground rods and provide permanent address label to each panel. Identify circuits in panel. All 5 panels. } ; {Activity date: 06/22/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - PARTIAL for 4 new panels for electric gates, pending 1 more. Please send (4) ECO Clearances to TEP for panels located at Building #3, #5, #9, and #21} |
|
| 10/11/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 10/11/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE ECO BLDG #13} ; {Activity date: 07/27/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO/BLDG #13} | |
| 12/08/2022 | COT - LCEL - Electrical Intermediate | Passed | Approved and complete | |
| 12/22/2022 | COT - LCEL - Electrical Final | Passed | 5 SERVICE PANELS FOR ENTRY GATES COMPLETE |