Permit: T22CM03435
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
4455 S HEATHER PL
Address NEW:
4455 S HEATHER PL
Apply Date:
05/05/2022
Applicant:
Herb Unruh
Description:
R-Workshop
Permit Reviews
Permit Number - T22CM03435
Permit Status: Complete
Permit Description: R-Workshop
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/05/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 05/27/2022 | COMPLETED |
| 09/01/2022 | RESUBMITTAL | 09/05/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03435
Permite Description: R-Workshop
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Preslab | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
| 10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03435
Permit Description: R-Workshop
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/14/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 11/16/2022 | COT - RSBU - Roof Nailing | Passed | ||
| 11/16/2022 | COT - LCBU - Framing | Passed | ||
| 11/16/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 12/21/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 03/24/2023 | COT - RSBU - Preslab | Passed | ||
| 03/24/2023 | COT - RSEL - Electrical Final | Passed | complete | |
| 03/24/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 03/24/2023 | COT - RSME - Mechanical Final | Passed | Mechanical equipment installed and operational. | |
| 03/24/2023 | RSBU - Building Final | Passed | Building is complete. Electrical panel is properly marked, GFCI outlets are installed and functional. Mechanical equipment is installed and functional. okay to issue level 4 C of O certificate. |