Permit: T22CM02967
Permit Details
Apply Date:
04/21/2022
Applicant:
Description:
New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Permit Reviews
Permit Number - T22CM02967
Permit Status: Complete
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/21/2022 | 3RD PARTY REVIEW - COMMERCIAL | 06/22/2022 | COMPLETED |
| 06/28/2022 | RESUBMITTAL | 08/11/2022 | COMPLETED |
| 08/17/2022 | RESUBMITTAL | 08/26/2022 | COMPLETED |
| 06/06/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/15/2023 | APPROVED |
| 03/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/13/2023 | APPROVED |
Conditions
Permit Number - T22CM02967
Permit Status: Complete
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
| Date | Description | Comments |
|---|---|---|
| 06/21/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 06/21/2022 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 06/21/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 06/21/2022 | SHOP DRAWINGS REQUIRED FOR METAL BUILDING. | |
| 08/26/2022 | Prior to permit issuance a General Contractor Letter (GCL) is required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02967
Permite Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Building Above Ceiling | N/A | Not Ready | |
| 10/26/2022 | COT - LCEL - Electrical Underground | N/A | Not Ready | |
| 10/26/2022 | PDSD Building Division Pre-Construction Meeting | N/A | Not Ready | |
| 10/26/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Not Ready | |
| 10/26/2022 | COT - LCME - Mechanical Intermediate | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - Roof Nailing | N/A | Not Ready | |
| 11/10/2022 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | partial approval for walls only, ok to two side |
| 12/15/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | seismic wires not attached to some lights |
| 11/04/2022 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | |
| 10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02967
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Total Completed Inspections - 22
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/26/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 09/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for TI and Shell Building T22C02964, okay to cover and continue} | |
| 10/04/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 10/04/2022 | COT - LCBU - Preslab | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap The above components are Ap for the shell of the future TI } |
|
| 10/04/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 11/10/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 11/16/2022 | COT - LCBU - Framing | Passed | ||
| 12/15/2022 | COT - LCEL - Outdoor Lighting | Passed | ||
| 12/15/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
| 12/15/2022 | COT - LCME - Mechanical Above Ceiling | Passed | ||
| 12/16/2022 | COT - LCEL - Electrical Intermediate | Passed | ||
| 02/16/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 02/16/2023 | ENGR Engineering Final | Passed | ||
| 06/09/2023 | TRSP - ROW - Notice of Completion | Passed | ||
| 02/16/2023 | COT - LCEL - Electrical Final | Passed | ||
| 02/16/2023 | COT - LCME - Mechanical Final | Passed | ||
| 02/16/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 02/16/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 02/17/2023 | COT - HCBU - Building Final | Passed | recommend for C/O level 4 | |
| 02/17/2023 | COT - LCBU - Building Final | Passed | ||
| 03/10/2023 | COT - LCPL - Backwater Valve | Passed | Back water valve is installed with 2 clean outs one before valve and one after. Okay to backfill trench. | |
| 06/09/2023 | COT - FCON - Fire - Final | Passed | ||
| 06/09/2023 | PDSD Building Division - Sign Final | Passed |