New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE

Permit Reviews

Permit Number - T22CM02967
Permit Status: Complete
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Start Date Submittal Complete Date Status  
04/21/2022 3RD PARTY REVIEW - COMMERCIAL 06/22/2022 COMPLETED Review Details
06/28/2022 RESUBMITTAL 08/11/2022 COMPLETED Review Details
08/17/2022 RESUBMITTAL 08/26/2022 COMPLETED Review Details
06/06/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/15/2023 APPROVED Review Details
03/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/13/2023 APPROVED Review Details

Conditions

Permit Number - T22CM02967
Permit Status: Complete
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Date Description Comments
06/21/2022 SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED.
06/21/2022 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
06/21/2022 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
06/21/2022 SHOP DRAWINGS REQUIRED FOR METAL BUILDING.
08/26/2022 Prior to permit issuance a General Contractor Letter (GCL) is required

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM02967
Permite Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Total Outstanding Inspections - 10
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Building Above Ceiling N/A Not Ready
10/26/2022 COT - LCEL - Electrical Underground N/A Not Ready
10/26/2022 PDSD Building Division Pre-Construction Meeting N/A Not Ready
10/26/2022 COT - LCPL - Medical Gas Preconstruction Mtg N/A Not Ready
10/26/2022 COT - LCME - Mechanical Intermediate N/A Not Ready
10/26/2022 COT - LCBU - Roof Nailing N/A Not Ready
11/10/2022 COT - LCPL - Plumbing Intermediate N/A Partial Pass partial approval for walls only, ok to two side
12/15/2022 COT - LCEL - Electrical Above Ceiling N/A Partial Pass seismic wires not attached to some lights
11/04/2022 COT - LCEL - Electrical Intermediate N/A Partial Pass
10/26/2022 COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM02967
Permit Description: New TI for 1 suite in structure (plans submitted to addressing for suite # but he is behind) THIS PE
Total Completed Inspections - 22
Date Description Inspector Results Comments
09/26/2022 COT - LCPL - Rough Soil Passed {Activity date: 09/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for TI and Shell Building T22C02964, okay to cover and continue}
10/04/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
10/04/2022 COT - LCBU - Preslab Passed {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap

The above components are Ap for the shell of the future TI

}
10/04/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 10/04/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
11/10/2022 COT - HCBU - Interior Shear Bracing Passed
11/16/2022 COT - LCBU - Framing Passed
12/15/2022 COT - LCEL - Outdoor Lighting Passed
12/15/2022 COT - LCPL - Plumbing Above Ceiling Passed
12/15/2022 COT - LCME - Mechanical Above Ceiling Passed
12/16/2022 COT - LCEL - Electrical Intermediate Passed
02/16/2023 COT - LCPL - Plumbing Final Passed
02/16/2023 ENGR Engineering Final Passed
06/09/2023 TRSP - ROW - Notice of Completion Passed
02/16/2023 COT - LCEL - Electrical Final Passed
02/16/2023 COT - LCME - Mechanical Final Passed
02/16/2023 PDSD Site/Engineering Division - Landscaping Passed
02/16/2023 PDSD Site/Engineering Division - NPPO Passed
02/17/2023 COT - HCBU - Building Final Passed recommend for C/O level 4
02/17/2023 COT - LCBU - Building Final Passed
03/10/2023 COT - LCPL - Backwater Valve Passed Back water valve is installed with 2 clean outs one before valve and one after. Okay to backfill trench.
06/09/2023 COT - FCON - Fire - Final Passed
06/09/2023 PDSD Building Division - Sign Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
ENVELOPE COMCHECK 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GCL 2967 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
HOLDRITE-30-SWHP-WM-SPEC-SHEET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
HVAC CALCULATIONS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
METAL BLDG CALCS 2 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
METAL BLDG CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
METAL BLDG 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2967 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PSA 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
FINAL SPECIAL INSPECTION REPORT CTG SIGNED-2023-06-06_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
ENVELOPE COMCHECK.PDF DOCUMENTS VIEW
GCL 2967.PDF DOCUMENTS VIEW
HOLDRITE-30-SWHP-WM-SPEC-SHEET.PDF DOCUMENTS VIEW
HVAC CALCULATIONS.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
PSA.PDF DOCUMENTS VIEW
PERMIT 2967.PDF DOCUMENTS VIEW
METAL BLDG CALCS #2.PDF DOCUMENTS VIEW
METAL BLDG CALCS.PDF DOCUMENTS VIEW
METAL BLDG.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
CABINETS TO GO (CHLORINATION REPORT)-2023-02-23_V1.PDF DOCUMENTS VIEW
CABINETS TO GO -AIR BALANCE REPORT_V1.PDF DOCUMENTS VIEW