Permit: T22CM02608
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
2915 E 2ND ST
Address NEW:
2915 E 2ND ST
Apply Date:
04/11/2022
Applicant:
Description:
Guest House & Porch
Permit Reviews
Permit Number - T22CM02608
Permit Status: Complete
Permit Description: Guest House & Porch
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/11/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 05/03/2022 | COMPLETED |
| 05/26/2022 | RESUBMITTAL | 06/08/2022 | COMPLETED |
| 09/29/2022 | REVISION - - 1ST | 10/03/2022 | COMPLETED |
Conditions
Permit Number - T22CM02608
Permit Status: Complete
Permit Description: Guest House & Porch
| Date | Description | Comments |
|---|---|---|
| 08/22/2022 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02608
Permite Description: Guest House & Porch
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/01/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 06/01/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 06/01/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 06/01/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 01/05/2023 | COT - RSEL - Construction Power | N/A | Not Applicable |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02608
Permit Description: Guest House & Porch
Total Completed Inspections - 14
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/27/2022 | COT - RSPL - Yard Water Line | Passed | {Activity date: 06/27/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Ok to backfill with clean material. } |
|
| 06/30/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 06/30/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} | |
| 07/07/2022 | COT - RSBU - Preslab | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 07/07/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 07/07/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} | |
| 08/24/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 08/24/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} | |
| 08/26/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 08/24/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval sheathing not stapled in several spots } |
|
| 09/16/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} | |
| 09/16/2022 | COT - LCBU - Framing | Passed | {Activity date: 09/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/24/2022; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Not ready please call with intermediate inspections } |
|
| 01/05/2023 | COT - RSME - Mechanical Final | Passed | ||
| 01/05/2023 | COT - RSEL - Electrical Final | Passed | ||
| 01/05/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 01/05/2023 | COT - RSEL - Outdoor Lighting | Passed | ||
| 01/05/2023 | RSBU - Building Final | Passed | ||
| 01/05/2023 | COT - RSEL - Electrical Underground | Passed |