Permit: T22CM02293
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
1241 W NAVAJO ST
Address NEW:
1241 W NAVAJO ST
Apply Date:
03/30/2022
Applicant:
Description:
R-enclose portion of existing porch for new laundry room. convert existing laundry room into new ba
Permit Reviews
Permit Number - T22CM02293
Permit Status: Complete
Permit Description: R-enclose portion of existing porch for new laundry room. convert existing laundry room into new ba
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/30/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 04/22/2022 | COMPLETED |
| 05/03/2022 | RESUBMITTAL | 05/06/2022 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T22CM02293
Permit Status: Complete
Permit Description: R-enclose portion of existing porch for new laundry room. convert existing laundry room into new ba
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/06/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02293
Permite Description: R-enclose portion of existing porch for new laundry room. convert existing laundry room into new ba
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/23/2022 | COT - RSBU - Roof Nailing | N/A | Canceled | {Activity date: 06/23/2022; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by NGARCIA3 - na} |
| 06/23/2022 | COT - RSPL - Sewer | N/A | Canceled | {Activity date: 06/23/2022; Status: Not Applicable; Inspector: DQUINN; Comment: Entered by NGARCIA3 - na Tied into main house drain } |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02293
Permit Description: R-enclose portion of existing porch for new laundry room. convert existing laundry room into new ba
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2022 | COT - RSBU - Preslab | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 06/03/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 06/23/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 06/23/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap Bath and laundry rough ok to backfill.} ; {Activity date: 06/03/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa Laundry rough in footing ok } |
|
| 08/04/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/04/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 08/04/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 08/04/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} | |
| 08/29/2022 | RSME - Mechanical Progress | Passed | {Activity date: 08/29/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} | |
| 12/08/2022 | COT - RSEL - Electrical Final | Passed | ||
| 12/08/2022 | COT - RSME - Mechanical Final | Passed | ||
| 12/08/2022 | COT - RSEL - Outdoor Lighting | Passed | ||
| 12/08/2022 | COT - RSPL - Plumbing Final | Passed | ||
| 12/08/2022 | RSBU - Building Final | Passed |