Permit: T22CM02153
Permit Details
Apply Date:
03/23/2022
Applicant:
Ian McDonald
Description:
TI: Office Remodel
Permit Reviews
Permit Number - T22CM02153
Permit Status: Complete
Permit Description: TI: Office Remodel
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/23/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 04/28/2022 | COMPLETED |
05/12/2022 | RESUBMITTAL | 06/14/2022 | COMPLETED |
07/06/2022 | RESUBMITTAL | 07/15/2022 | COMPLETED |
03/17/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/21/2023 | APPROVED |
Conditions
Permit Number - T22CM02153
Permit Status: Complete
Permit Description: TI: Office Remodel
Date | Description | Comments |
---|---|---|
05/12/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM02153
Permite Description: TI: Office Remodel
Total Outstanding Inspections - 14
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - LCBU - Preslab | N/A | Not Ready | |
10/27/2022 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
11/08/2022 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | office 102, 103 104. south end wall okay for drywall. |
12/12/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | 107 bathroom. okay for hard lid. |
12/12/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Partial Pass | 107 okay for hard lid. |
12/12/2022 | COT - LCBU - Building Above Ceiling | N/A | Partial Pass | room 107 okay for hard lid. |
12/12/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | 107. okay for hard lid. supply lines are completed. |
01/31/2023 | COT - LCME - Mechanical Progress | N/A | Partial Pass | kitchen area east of building okay to proceed. |
12/09/2022 | COT - LCEL - Electrical Progress | N/A | Partial Pass | partial approval for restroom in wall |
10/26/2022 | COT - LCME - Mechanical Final | N/A | Not Ready | |
03/23/2023 | COT - FCON - Sprinkler - Final | N/A | Partial Pass | Annual sprinkler inspection needed. |
10/27/2022 | COT - LCBU - Building Final | N/A | Not Ready | |
10/26/2022 | COT - LCPL - Plumbing Final | N/A | Not Ready | |
COT - FCON - Fire - Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM02153
Permit Description: TI: Office Remodel
Total Completed Inspections - 27
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/30/2022 | COT - HCPL - Rough Soil | Passed | grease trap is under pressure. no leaks. | |
11/30/2022 | COT - LCBU - Framing | Passed | ||
01/05/2023 | BULD - Electrical Clearance | Passed | ||
01/12/2023 | COT - LCPL - Gas Pressure Test | Passed | gas lines under pressure | |
01/12/2023 | COT - HCBU - Preslab | Passed | ||
01/17/2023 | COT - HCBU - Framing | Passed | South exterior wall. North kitchen wall. room. 114 kitchen 115 kitchen | |
01/17/2023 | COT - LCEL - Electrical Intermediate | Passed | South exterior wall. North kitchen wall. 124 cable tray room. 114 kitchen 115 kitchen 122 dry storage 125 dry storage . | |
01/23/2023 | COT - HCBU - Interior Shear Bracing | Passed | both structural walls are complete with Sheetrock and screw placement correct. | |
02/16/2023 | COT - LCEL - Service Upgrade | Passed | ||
02/17/2023 | COT - LCEL - Electrical Above Ceiling | Passed | all boxes are properly marked. lighting fixtures are installed and functional. | |
02/17/2023 | COT - LCME - Mechanical Above Ceiling | Passed | register are in grid ceilings and ductwork attached. | |
02/17/2023 | COT - LCBU - Building Above Ceiling | Passed | all trades are completed okay to install ceiling tiles. | |
02/17/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | all plumbing is complete. | |
03/23/2023 | COT - LCME - Mechanical Progress | Passed | ||
03/29/2023 | COT - LCPL - Plumbing Progress | Passed | ||
03/29/2023 | COT - LCEL - Electrical Progress | Passed | ||
03/29/2023 | COT - LCBU - Building Progress | Passed | ||
04/05/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
05/03/2023 | COT - LCME - Mechanical Final | Passed | ||
05/03/2023 | COT - LCEL - Electrical Final | Passed | ||
05/03/2023 | COT - LCME - Kitchen Hood | Passed | ||
05/05/2023 | COT - FCON - Sprinkler - Final | Passed | ||
05/30/2023 | COT - FCON - Alarm - Final | Passed | ||
05/30/2023 | COT - LCBU - Building Final | Passed | recommend C/O | |
05/30/2023 | COT - LCPL - Plumbing Final | Passed | ||
06/20/2023 | COT - FCON - Fire - Final | Passed | ||
06/20/2023 | COT - FCON - Hood System - Final | Passed |