Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Address:
3355 S 6TH AV
Apply Date:
03/23/2022
Applicant:
Ian McDonald
Description:
TI: Office Remodel

Permit Reviews

Permit Number - T22CM02153
Permit Status: Complete
Permit Description: TI: Office Remodel
Start Date Submittal Complete Date Status  
03/23/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 04/28/2022 COMPLETED Review Details
05/12/2022 RESUBMITTAL 06/14/2022 COMPLETED Review Details
07/06/2022 RESUBMITTAL 07/15/2022 COMPLETED Review Details
03/17/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/21/2023 APPROVED Review Details

Conditions

Permit Number - T22CM02153
Permit Status: Complete
Permit Description: TI: Office Remodel
Date Description Comments
05/12/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM02153
Permite Description: TI: Office Remodel
Total Outstanding Inspections - 14
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCBU - Preslab N/A Not Ready
10/27/2022 COT - LCPL - Plumbing Intermediate N/A Not Ready
11/08/2022 COT - LCEL - Electrical Intermediate N/A Partial Pass office 102, 103 104. south end wall okay for drywall.
12/12/2022 COT - LCEL - Electrical Above Ceiling N/A Partial Pass 107 bathroom. okay for hard lid.
12/12/2022 COT - LCME - Mechanical Above Ceiling N/A Partial Pass 107 okay for hard lid.
12/12/2022 COT - LCBU - Building Above Ceiling N/A Partial Pass room 107 okay for hard lid.
12/12/2022 COT - LCPL - Plumbing Above Ceiling N/A Partial Pass 107. okay for hard lid. supply lines are completed.
01/31/2023 COT - LCME - Mechanical Progress N/A Partial Pass kitchen area east of building okay to proceed.
12/09/2022 COT - LCEL - Electrical Progress N/A Partial Pass partial approval for restroom in wall
10/26/2022 COT - LCME - Mechanical Final N/A Not Ready
03/23/2023 COT - FCON - Sprinkler - Final N/A Partial Pass Annual sprinkler inspection needed.
10/27/2022 COT - LCBU - Building Final N/A Not Ready
10/26/2022 COT - LCPL - Plumbing Final N/A Not Ready
COT - FCON - Fire - Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T22CM02153
Permit Description: TI: Office Remodel
Total Completed Inspections - 27
Date Description Inspector Results Comments
11/30/2022 COT - HCPL - Rough Soil Passed grease trap is under pressure. no leaks.
11/30/2022 COT - LCBU - Framing Passed
01/05/2023 BULD - Electrical Clearance Passed
01/12/2023 COT - LCPL - Gas Pressure Test Passed gas lines under pressure
01/12/2023 COT - HCBU - Preslab Passed
01/17/2023 COT - HCBU - Framing Passed South exterior wall. North kitchen wall. room. 114 kitchen 115 kitchen
01/17/2023 COT - LCEL - Electrical Intermediate Passed South exterior wall. North kitchen wall. 124 cable tray room. 114 kitchen 115 kitchen 122 dry storage 125 dry storage .
01/23/2023 COT - HCBU - Interior Shear Bracing Passed both structural walls are complete with Sheetrock and screw placement correct.
02/16/2023 COT - LCEL - Service Upgrade Passed
02/17/2023 COT - LCEL - Electrical Above Ceiling Passed all boxes are properly marked. lighting fixtures are installed and functional.
02/17/2023 COT - LCME - Mechanical Above Ceiling Passed register are in grid ceilings and ductwork attached.
02/17/2023 COT - LCBU - Building Above Ceiling Passed all trades are completed okay to install ceiling tiles.
02/17/2023 COT - LCPL - Plumbing Above Ceiling Passed all plumbing is complete.
03/23/2023 COT - LCME - Mechanical Progress Passed
03/29/2023 COT - LCPL - Plumbing Progress Passed
03/29/2023 COT - LCEL - Electrical Progress Passed
03/29/2023 COT - LCBU - Building Progress Passed
04/05/2023 COT - LCME - Mechanical Intermediate Passed
05/03/2023 COT - LCME - Mechanical Final Passed
05/03/2023 COT - LCEL - Electrical Final Passed
05/03/2023 COT - LCME - Kitchen Hood Passed
05/05/2023 COT - FCON - Sprinkler - Final Passed
05/30/2023 COT - FCON - Alarm - Final Passed
05/30/2023 COT - LCBU - Building Final Passed recommend C/O
05/30/2023 COT - LCPL - Plumbing Final Passed
06/20/2023 COT - FCON - Fire - Final Passed
06/20/2023 COT - FCON - Hood System - Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
AIR BALANCE - MOBILE MEALS OF SOUTHERN ARIZONA FLOOR PLAN_V1.PDF DOCUMENTS VIEW
AIR BALANCE - MOBILE MEALS OF SOUTHERN AZ. - REPORT_V1.PDF DOCUMENTS VIEW
CHOLRINATION_STERILIZATION - CATALINA MECH. - MOBILE MEALS LAB RESULTS-2023-03-16_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PLAN SET MOBILE MEALS - NO WALK IN COOLER.PDF CONSTRPLANS VIEW
PLAN SET_TI WORK ONLY.PDF CONSTRPLANS VIEW