Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM01923
Permit Details
Apply Date:
03/16/2022
Applicant:
Troy White
Description:
Interior renovation with small addition.
Permit Reviews
Permit Number - T22CM01923
Permit Status: Complete
Permit Description: Interior renovation with small addition.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/16/2022 | 3RD PARTY REVIEW - COMMERCIAL TI | 05/18/2022 | COMPLETED |
08/11/2022 | 3RD PARTY REVIEW - COMMERCIAL | 09/08/2022 | COMPLETED |
10/01/2022 | RESUBMITTAL | 10/20/2022 | COMPLETED |
06/28/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/29/2023 | REQUIRES RESUBMIT |
06/30/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 06/30/2023 | APPROVED |
07/24/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 07/25/2023 | APPROVED |
06/22/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/26/2023 | REQUIRES RESUBMIT |
Conditions
Permit Number - T22CM01923
Permit Status: Complete
Permit Description: Interior renovation with small addition.
Date | Description | Comments |
---|---|---|
05/18/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01923
Permite Description: Interior renovation with small addition.
Total Outstanding Inspections - 15
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/27/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Applicable | There are no interior shear walls on this project. |
01/18/2023 | COT - LCBU - Framing | N/A | Partial Pass | rough framing is 75% complete on walls & ceiling. |
12/21/2022 | COT - LCBU - Building Progress | N/A | Partial Pass | |
05/19/2023 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | |
06/21/2023 | COT - LCBU - Sustainability | N/A | Not Applicable | Not required. Project is not LEED Certified. |
04/05/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | partial approval for break room and office in SW corner only mechanical and plumbing passed |
02/01/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | Receiving room #113, Hall -2, Starch room #116, Break room #118, Restroom #121 and 122, Janitors room #123, Office Admin #100, South end of Work room #115 okay to proceed. |
02/01/2023 | COT - LCME - Mechanical Progress | N/A | Partial Pass | work room #115 okay to proceed. |
02/01/2023 | COT - LCPL - Plumbing Progress | N/A | Partial Pass | Receiving room #113, Hall -2, Starch room #116, Break room #118, Restroom #121 and 122, Janitors room #123, Office Admin #100, South end of Work room #115 above ceiling and intermediate. |
02/01/2023 | COT - LCPL - Plumbing Intermediate | N/A | Partial Pass | Receiving room #113, Hall -2, Starch room #116, Break room #118, Restroom #121 and 122, Janitors room #123, Office Admin #100, South end of Work room #115 okay for 1 side drywall. |
06/23/2023 | COT - LCEL - Electrical Final | N/A | Re-inspection required | 6/23/23: outlets within 6 feet of sink required to be GFCI, |
07/19/2023 | BULD - Electrical Clearance | N/A | Not Applicable | |
06/23/2023 | COT - LCME - Mechanical Final | N/A | Re-inspection required | 6/23/23: install a OSHA approved ladder extendable handle at top of roof ladder. More items may be added after access to the roof. |
07/19/2023 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 1 in air gap required on mop sink and floor grates |
06/23/2023 | COT - LCBU - Building Final | N/A | Re-inspection required |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01923
Permit Description: Interior renovation with small addition.
Total Completed Inspections - 30
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/12/2022 | COT - LCPL - Rough Soil | Passed | building all under pressure. okay to back fill. shading required. | |
12/15/2022 | COT - LCEL - Electrical Underground | Passed | Electric service to be run across roof of structure…no electric underground. | |
12/19/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
12/19/2022 | COT - LCBU - Preslab | Passed | okay for concrete. | |
12/21/2022 | COT - HCPL - Rough Soil | Passed | grease trap interceptor connected and under pressure. shading required | |
12/21/2022 | COT - HCPL - Sewer | Passed | okay to backfill. shading required | |
02/27/2023 | COT - LCBU - Framing | Passed | Framing is complete. Okay to sheet rock both sides of walls. | |
02/27/2023 | COT - HCPL - Yard Water Line | Passed | Water supply for building is connected to the back-flow preventer at the street. Water has been turned on to pressurize the system with no leaks. Okay to backfill trenches. | |
04/28/2023 | COT - LCEL - Construction Power | Passed | Electrical conduit from new transformer pad to building is installed in trench. Okay to backfill trench and install ribbon tape one foot below grade. | |
05/05/2023 | COT - LCEL - Grounding/Bonding | Passed | Grounding rods are in place with copper wire from panel boxes to rods connected. Okay to backfill trenches and compact. | |
05/05/2023 | COT - LCBU - Building Progress | Passed | FRP is installed on walls. Grid ceiling is installed in office areas and prep areas. Walk-ins are installed. Electricians are pulling wires from panel to outlets. | |
05/19/2023 | COT - LCEL - Electrical Progress | Passed | ||
06/21/2023 | COT - BULD - SWG Clearance | Passed | Gas line is under pressure and holding 15# of air. Okay to connect gas to building. | |
06/21/2023 | COT - LCPL - Gas Pressure Test | Passed | Gas line is under pressure and holding 15# of air. Okay to connect gas to building. | |
06/21/2023 | COT - LCEL - Electrical Above Ceiling | Passed | Electrical above ceiling is complete. Okay to install ceiling tiles in grid ceiling. | |
06/21/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | 6-21-23: Plumbing above ceiling is complete. Okay to install ceiling tiles in grid ceiling. | |
06/21/2023 | COT - LCBU - Building Above Ceiling | Passed | Mechanical, plumbing, & electrical above ceiling is complete. Okay to install ceiling tile in grid ceiling. | |
06/21/2023 | COT - LCME - Mechanical Above Ceiling | Passed | Mechanical above ceiling is complete. Okay to install ceiling tile in grid ceiling. | |
06/21/2023 | COT - LCME - Mechanical Intermediate | Passed | Mechanical is complete and operational. | |
06/21/2023 | COT - LCME - Mechanical Progress | Passed | Mechanical is complete and operational. | |
06/21/2023 | COT - LCEL - Outdoor Lighting | Passed | Exterior lights are flush mounted to exterior walls and point directly to the ground. 3 lights on the front and rear of building and 4 lights on each side of building. | |
06/21/2023 | COT - LCPL - Plumbing Progress | Passed | Plumbing is complete and operational. | |
06/21/2023 | COT - LCPL - Plumbing Intermediate | Passed | Plumbing is complete and operational. | |
06/21/2023 | COT - LCME - Kitchen Hood | Passed | Kitchen hood is installed and functional. Smoke test was preformed by the annul system installer. | |
06/23/2023 | SITE - Zoning Final | Passed | ||
06/29/2023 | COT - LCEL - Electrical Final | Passed | ||
07/19/2023 | COT - FCON - Fire - Final | Passed | ||
07/21/2023 | COT - LCME - Mechanical Final | Passed | ||
07/21/2023 | COT - LCPL - Plumbing Final | Passed | ||
07/24/2023 | COT - LCBU - Building Final | Passed | see previous results |