Inspection Status: Not Ready
Inspection History: COT - LCPL - Plumbing Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCPL - Plumbing Above Ceiling |
|
Not Ready |
|
| 02/01/2023 |
COT - LCPL - Plumbing Above Ceiling |
|
Partial Pass |
Receiving room #113, Hall -2, Starch room #116, Break room #118, Restroom #121 and 122, Janitors room #123, Office Admin #100, South end of Work room #115 okay to proceed. |
| 02/22/2023 |
COT - LCPL - Plumbing Above Ceiling |
|
Partial Pass |
water supply lines are installed along west wall for restrooms & janitors closet. |
| 02/27/2023 |
COT - LCPL - Plumbing Above Ceiling |
|
Partial Pass |
Plumbing from restrooms to riser room is complete. Plumber working on piping for main supply and water heaters. |
| 04/28/2023 |
COT - LCPL - Plumbing Above Ceiling |
|
Partial Pass |
4-28-23: Fire riser pump is installed has not been pressurized. |
| 06/21/2023 |
COT - LCPL - Plumbing Above Ceiling |
|
Passed |
6-21-23: Plumbing above ceiling is complete. Okay to install ceiling tiles in grid ceiling. |