Permit: T22CM01455
Permit Details
Apply Date:
03/01/2022
Applicant:
Brent Stevens
Description:
210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities.Bldg 7
Permit Reviews
Permit Number - T22CM01455
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities.Bldg 7
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/01/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/02/2022 | COMPLETED |
06/30/2022 | RESUBMITTAL | 07/19/2022 | COMPLETED |
08/12/2022 | RESUBMITTAL | 08/29/2022 | COMPLETED |
09/13/2022 | RESUBMITTAL | 09/26/2022 | COMPLETED |
10/03/2022 | RESUBMITTAL | 10/06/2022 | COMPLETED |
06/05/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/06/2024 | APPROVED |
06/18/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/21/2024 | APPROVED |
06/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/18/2024 | APPROVED |
Conditions
Permit Number - T22CM01455
Permit Status: Complete
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities.Bldg 7
Date | Description | Comments |
---|---|---|
10/06/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
10/06/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
10/06/2022 | SPECIAL INSPECTION IS REQUIRED FOR WATER CHLORINATION REQUIRED PRIOR TO FINAL INSPECTION. | |
10/06/2022 | SPECIAL INSPECTION IS REQUIRED FOR AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR WOOD FLOOR JOISTS. | |
10/06/2022 | SHOP DRAWINGS REQUIRED FOR TRUSSES, WOOD ROOF TRUSSES. | |
10/06/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE | |
06/12/2024 | PCRWRD requests that the City of Tucson, add the PCRWRD Condition to the COT building permit #T22CM01449:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE DISCHARGE AUTHORIZATION IS ISSUED BY PDEQ FOR THE PRIVATE SEWER #P22SD00039 Gerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503 | |
06/18/2024 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01455
Permite Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities.Bldg 7
Total Outstanding Inspections - 17
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/09/2023 | COT - LCME - Mechanical Above Ceiling | N/A | Partial Pass | South breezeway. |
10/09/2023 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | Above ceiling firewalls. |
10/09/2023 | COT - LCPL - Plumbing Roof Drains | N/A | Partial Pass | South breezeway. |
10/09/2023 | COT - LCBU - Framing | N/A | Partial Pass | South breezeway. |
10/09/2023 | COT - LCEL - Electrical Above Ceiling | N/A | Partial Pass | South breezeway. |
10/09/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Partial Pass | South breezeway. |
12/07/2023 | COT - LCPL - Plumbing Intermediate | N/A | Not Ready | |
12/07/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
12/07/2023 | COT - LCEL - Electrical Intermediate | N/A | Not Ready | |
10/26/2022 | FCON – OH Piping & Hydro | N/A | Not Ready | |
10/26/2022 | COT - FCON - Alarm - Final | N/A | Not Ready | |
06/24/2024 | COT - LCME - Mechanical Final | N/A | Partial Pass | 6/24/24: south half of building 7 partial pass. |
07/15/2024 | COT - LCPL - Plumbing Final | N/A | Partial Pass | 6/24/24: south half of building 7 partial pass. 7/15/24: north half passed. Pending fire inspection |
10/26/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | |
10/26/2022 | COT - FCON - Fire - Final | N/A | Not Ready | |
06/24/2024 | COT - LCBU - Building Final | N/A | Partial Pass | 6/24/24: south half of building 7 partial pass. |
06/24/2024 | COT - LCEL - Electrical Final | N/A | Partial Pass | 6/24/24: south half of building 7 partial pass. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01455
Permit Description: 210 unit apartment complex with clubhouse, landscaped courtyard and pool, and other amenities.Bldg 7
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/24/2023 | COT - LCBU - Excavation/Rebar/Zoning | Passed | ||
01/31/2023 | COT - LCPL - Rough Soil | Passed | ||
06/16/2023 | COT - LCEL - Electrical Underground | Passed | ||
06/16/2023 | COT - LCBU - Preslab | Passed | ||
06/28/2023 | COT - LCBU - Roof Nailing | Passed | ||
07/17/2023 | COT - LCBU - Exterior Clips/Sheathing | Passed | remainder of third floor | |
10/09/2023 | COT - LCPL - Sewer | Passed | ||
10/09/2023 | COT - LCPL - Backwater Valve | Passed | ||
10/20/2023 | COT - LCME - Mechanical Above Ceiling | Passed | 10/20/23:Middle Breezeway 6 South units. | |
11/15/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
11/17/2023 | COT - LCPL - Plumbing Roof Drains | Passed | ||
11/17/2023 | COT - LCBU - Framing | Passed | ||
11/17/2023 | COT - LCEL - Electrical Above Ceiling | Passed | ||
11/17/2023 | COT - LCPL - Plumbing Above Ceiling | Passed | ||
12/08/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
12/08/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
12/08/2023 | COT - LCBU - Firewall/Fire Barrier/Firestop | Passed | ||
12/08/2023 | COT - LCEL - Electrical Intermediate | Passed | ||
12/11/2023 | COT - LCME - Mechanical Progress | Passed | ||
12/11/2023 | COT - LCEL - Electrical Progress | Passed | ||
12/11/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
12/11/2023 | COT - LCBU - Building Progress | Passed | ||
12/11/2023 | COT - LCPL - Plumbing Progress | Passed | ||
04/29/2024 | COT - LCEL - Service Upgrade | Passed | 4/19/24: South Electrical Gear / Meter bank ECO CLEARANCE for (HPG1,GARG1,7101,7201,7301,7102,7203,7103,7302,7202,7303,7104,7204,7304,7105,7205,7305,7306,7206,7106) 4/29/24: North Electrical Gear / Meter Bank ECO CLEARANCE for (HPG2,7107,7108,7109,7110,7111,7112,7113,7114,7207,7208,7209,7210,7211,7212,7213,7214,7307,7308,7309,7310,7311,7312,7313,7314) |
|
06/11/2024 | COT - FCON - Alarm - Final | Passed | ||
06/24/2024 | COT - LCBU - Sustainability | Passed | ||
07/09/2024 | ENGR Engineering Final | Passed | ||
07/15/2024 | COT - LCEL - Outdoor Lighting | Passed | ||
07/16/2024 | COT - FCON - Sprinkler - Final | Passed | ||
07/16/2024 | COT - LCBU - Building Final | Passed | ||
07/16/2024 | COT - LCEL - Electrical Final | Passed |