Permit: T22CM01271
Permit Details
Apply Date:
02/22/2022
Applicant:
Erich Olds
Description:
3rd Party - New Commercial Storage Facility
Permit Reviews
Permit Number - T22CM01271
Permit Status: In review
Permit Description: 3rd Party - New Commercial Storage Facility
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/22/2022 | 3RD PARTY REVIEW - COMMERCIAL | 07/28/2022 | COMPLETED |
02/28/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/03/2025 | APPROVED |
02/27/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/27/2025 | REQUIRES RESUBMIT |
06/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2023 | REQUIRES RESUBMIT |
11/21/2023 | RESTAMP - COMMERCIAL v.1 | 11/21/2023 | APPROVED |
11/20/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/21/2023 | APPROVED |
04/21/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | N/A | IN REVIEW |
11/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2023 | REQUIRES RESUBMIT |
02/24/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 02/25/2025 | APPROVED |
04/07/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/14/2025 | REQUIRES RESUBMIT |
05/24/2024 | COMMERCIAL REVIEW - FULL v.1 | 05/24/2024 | REQUIRES RESUBMIT |
03/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/01/2024 | APPROVED |
02/21/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/21/2024 | REQUIRES RESUBMIT |
05/28/2024 | COMMERCIAL REVIEW - FULL v.2 | 06/12/2024 | APPROVED |
03/06/2025 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/11/2025 | APPROVED |
11/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM01271
Permit Status: In review
Permit Description: 3rd Party - New Commercial Storage Facility
Total Outstanding Activity Conditions - 3
Date | Name |
---|---|
04/03/2024 | EFIS Designs must be submitted and approved prior to final. |
04/03/2024 | Metal Stairs Designs must be submitted and approved prior to final. |
04/03/2024 | Metal Stud Designs Designs must be submitted and approved prior to final. |
Conditions
Permit Number - T22CM01271
Permit Status: In review
Permit Description: 3rd Party - New Commercial Storage Facility
Date | Description | Comments |
---|---|---|
11/20/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. | |
07/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
04/03/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. | |
06/18/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
04/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
04/03/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. | |
04/03/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
04/03/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
04/03/2024 | Masonry Inspection Report submittal review is required. | |
04/03/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. | |
04/03/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
11/20/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. | |
11/22/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. | |
04/03/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
04/03/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
Outstanding Inspections
Permit Status: In Review
Permit Number: T22CM01271
Permite Description: 3rd Party - New Commercial Storage Facility
Total Outstanding Inspections - 11
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/23/2024 | COT - HCBU - Building Progress | N/A | Partial Pass | Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout Partial approval for south stair tower, and two elevator towers Partial approval for south stair tower 3rd lift Partial approval for three towers third lift, north tower 2nd lift only Partial approval for south three towers 4th lift and notch tower third lift ok to grout 4/25/24: partial approval for all four towers 5th lift ok to grout. 4/29/24: partial approval for all four towers 6th lift ok to grout @28'. 5/2/24:partial approval for all four towers 7th lift ok to grout @32' 5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers. 5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower. 7/1/24: third floor decking fastened per schedule ok to proceed. 7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement. 7/17/24: not ready 7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed 7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill. 8/7/24: DensGlass sheathing fastened per schedule first floor complete. 8/13/24: okay to cover galvanized roofing 9/24/24: first floor electrical in wall passed, first floor framing complete. 9/25/25: 2nd and 3rd floor framing at exterior walls per plan ok to proceed. 2nd floor electrical in wall at bathroom passed, plumbing at 2nd floor and first floor passed. 10/23/24: drywall nailing per plan at first floor sales area. Framing per plan at mechanical shaft at all three floors. |
06/05/2024 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 6/5/24: x-bracing per plan at first floor ok to proceed |
06/07/2024 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 6/7/24: second floor decking fastened per schedule ok to proceed. |
03/08/2024 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans 3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed. |
10/29/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass | |
03/15/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
03/06/2024 | COT - HCPL - Sewer | N/A | Partial Pass | |
02/18/2025 | COT - HCEL - Electrical Final | N/A | Not Ready | |
02/21/2025 | COT - HCME - Mechanical Final | N/A | Not Ready | 2-21-25, not ready. |
10/01/2024 | COT - FCON - Sprinkler - Final | N/A | Re-inspection required | Looked at fire line under pressure. OK to bury. Still need flush. Waiting for permit to be issued. |
02/19/2025 | COT - FCON - Fire - Final | N/A | Partial Pass | Approved for level 3 TCO 1st floor only. FDC sign with correct address. FDC locking caps. Knox boxes(2) with labeled keys. Address identification. FACP sign. Exit sign 1st floor SE of drive through.Exit sign NW hall 2nd floor.1st floor W stair exit sign and exit discharge lights shall be illuminated with A/C loss. EM lights 3rd floor E corridor |
Completed Inspections
Permit Status: In Review
Permit Number: T22CM01271
Permit Description: 3rd Party - New Commercial Storage Facility
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/08/2024 | COT - HCBU - Masonry Pregrout | Passed | Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans 3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed. |
|
04/04/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 4/4/24: Footer and second half of preslab ok to pour concrete. | |
07/02/2024 | COT - HCBU - Framing | Passed | ||
10/08/2024 | COT - HCPL - Yard Water Line | Passed | ||
10/29/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 10/29/2024 | |
01/15/2025 | COT - HCEL - Outdoor Lighting | Passed | OK to cover trenching throughout | |
01/27/2025 | COT - HCME - Mechanical Above Ceiling | Passed | Ok to set ceiling tiles in office and break areas. | |
01/27/2025 | COT - HCEL - Electrical Above Ceiling | Passed | Ok to set ceiling tiles in Office area and break area. | |
01/27/2025 | COT - HCPL - Plumbing Above Ceiling | Passed | Office and break areas; OK to set ceiling tiles. | |
02/18/2025 | COT - HCBU - Building Above Ceiling | Passed | ||
02/18/2025 | COT - HCBU - Building Progress | Passed | ||
02/18/2025 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
02/18/2025 | COT - HCBU - Interior Shear Bracing | Passed | ||
02/19/2025 | COT - HCBU - Preslab | Passed | ||
02/18/2025 | COT - HCBU - Roof Nailing | Passed | ||
02/18/2025 | COT - HCBU - Stem Wall/Retaining Wall | Passed | ||
02/18/2025 | COT - HCEL - Electrical Intermediate | Passed | ||
02/18/2025 | COT - HCEL - Electrical Underground | Passed | ||
02/21/2025 | COT - LCBU - Building Final | Passed | 2-21-25, building final approved. | |
02/21/2025 | COT - HCBU - Building Final | Passed | 2-21-25, building final approved. | |
02/21/2025 | COT - HCPL - Sewer | Passed | ||
02/21/2025 | COT - HCPL - Rough Soil | Passed | ||
02/21/2025 | COT - HCME - Mechanical Intermediate | Passed | ||
02/21/2025 | COT - HCPL - Plumbing Roof Drains | Passed | ||
02/21/2025 | COT - HCPL - Plumbing Intermediate | Passed | ||
02/21/2025 | COT - HCEL - Electrical Final | Passed | 2-21-25, electrical final approved. | |
02/25/2025 | TRSP - ROW - Final/Close-Out | Passed | ||
02/28/2025 | ENGR Engineering Final | Passed | No issues found, CO Ready | |
03/05/2025 | COT - HCBU - TCO | Passed | 3-5-25, approved for 1st floor Level 3 TCO. | |
03/06/2025 | COT - FCON - Sprinkler - Final | Passed | ||
04/01/2025 | COT - FCON - Fire - Final | Passed |