Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T22CM01271
Permit Details
Apply Date:
02/22/2022
Applicant:
Erich Olds
Description:
New Commercial Storage Facility
Permit Reviews
Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/22/2022 | 3RD PARTY REVIEW - COMMERCIAL | 07/28/2022 | COMPLETED |
06/14/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2023 | REQUIRES RESUBMIT |
11/21/2023 | RESTAMP - COMMERCIAL v.1 | 11/21/2023 | APPROVED |
11/20/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/21/2023 | APPROVED |
11/20/2023 | COMMERCIAL REVIEW - FULL v.1 | 11/20/2023 | REQUIRES RESUBMIT |
05/24/2024 | COMMERCIAL REVIEW - FULL v.1 | 05/24/2024 | REQUIRES RESUBMIT |
03/04/2024 | COMMERCIAL REVIEW - FULL v.2 | 04/01/2024 | APPROVED |
02/21/2024 | COMMERCIAL REVIEW - FULL v.1 | 02/21/2024 | REQUIRES RESUBMIT |
05/28/2024 | COMMERCIAL REVIEW - FULL v.2 | 06/12/2024 | APPROVED |
11/27/2023 | COMMERCIAL REVIEW - FULL v.1 | 02/05/2024 | APPROVED |
Outstanding Activity Conditions
Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Total Outstanding Activity Conditions - 17
Date | Name |
---|---|
04/03/2024 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
04/03/2024 | Masonry Inspection Report submittal review is required. |
04/03/2024 | Automatic Fire Sprinklers Designs must be submitted and approved prior to final. |
04/03/2024 | EFIS Designs must be submitted and approved prior to final. |
04/03/2024 | Fire Alams Designs must be submitted and approved prior to final. |
04/03/2024 | Metal Stairs Designs must be submitted and approved prior to final. |
04/03/2024 | Metal Stud Designs Designs must be submitted and approved prior to final. |
04/03/2024 | SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
04/03/2024 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. |
04/03/2024 | WATER STERILIZATION REPORT IS REQUIRED. |
11/20/2023 | AIR BALANCING/COMMISSIONING REPORT IS REQUIRED. |
11/22/2023 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. |
Conditions
Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Date | Description | Comments |
---|---|---|
07/28/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
06/18/2024 | Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit. | |
11/20/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Issued
Permit Number: T22CM01271
Permite Description: New Commercial Storage Facility
Total Outstanding Inspections - 9
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/06/2024 | COT - HCPL - Sewer | N/A | Partial Pass | |
03/08/2024 | COT - HCBU - Stem Wall/Retaining Wall | N/A | Partial Pass | Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans 3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed. |
03/15/2024 | COT - HCEL - Electrical Underground | N/A | Partial Pass | |
06/05/2024 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 6/5/24: x-bracing per plan at first floor ok to proceed |
06/07/2024 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 6/7/24: second floor decking fastened per schedule ok to proceed. |
06/14/2024 | COT - HCBU - Preslab | N/A | Partial Pass | 6/13/24: Slab on deck 2nd floor Gridline A-B.5/1-7.3 reinforcement per plans. 6/14/24: slab on deck 2nd floor Gridline B.5-Z.3/1-17.3 reinforced per plans |
10/01/2024 | COT - FCON - Sprinkler - Final | N/A | Re-inspection required | Looked at fire line under pressure. OK to bury. Still need flush. Waiting for permit to be issued. |
10/23/2024 | COT - HCBU - Building Progress | N/A | Partial Pass | Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout Partial approval for south stair tower, and two elevator towers Partial approval for south stair tower 3rd lift Partial approval for three towers third lift, north tower 2nd lift only Partial approval for south three towers 4th lift and notch tower third lift ok to grout 4/25/24: partial approval for all four towers 5th lift ok to grout. 4/29/24: partial approval for all four towers 6th lift ok to grout @28'. 5/2/24:partial approval for all four towers 7th lift ok to grout @32' 5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers. 5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower. 7/1/24: third floor decking fastened per schedule ok to proceed. 7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement. 7/17/24: not ready 7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed 7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill. 8/7/24: DensGlass sheathing fastened per schedule first floor complete. 8/13/24: okay to cover galvanized roofing 9/24/24: first floor electrical in wall passed, first floor framing complete. 9/25/25: 2nd and 3rd floor framing at exterior walls per plan ok to proceed. 2nd floor electrical in wall at bathroom passed, plumbing at 2nd floor and first floor passed. 10/23/24: drywall nailing per plan at first floor sales area. Framing per plan at mechanical shaft at all three floors. |
10/29/2024 | COT - HCEL - Electrical Intermediate | N/A | Partial Pass |
Completed Inspections
Permit Status: Issued
Permit Number: T22CM01271
Permit Description: New Commercial Storage Facility
Total Completed Inspections - 5
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/08/2024 | COT - HCBU - Masonry Pregrout | Passed | Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans 3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed. |
|
04/04/2024 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 4/4/24: Footer and second half of preslab ok to pour concrete. | |
07/02/2024 | COT - HCBU - Framing | Passed | ||
10/08/2024 | COT - HCPL - Yard Water Line | Passed | ||
10/29/2024 | BULD - Electrical Clearance | Passed | Clearance for TEP ECO. 10/29/2024 |