Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Apply Date:
02/22/2022
Applicant:
Erich Olds
Description:
New Commercial Storage Facility

Permit Reviews

Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Start Date Submittal Complete Date Status  
02/22/2022 3RD PARTY REVIEW - COMMERCIAL 07/28/2022 COMPLETED Review Details
06/14/2023 COMMERCIAL REVIEW - FULL v.1 11/20/2023 REQUIRES RESUBMIT Review Details
11/21/2023 RESTAMP - COMMERCIAL v.1 11/21/2023 APPROVED Review Details
11/20/2023 COMMERCIAL REVIEW - FULL v.2 11/21/2023 APPROVED Review Details
11/20/2023 COMMERCIAL REVIEW - FULL v.1 11/20/2023 REQUIRES RESUBMIT Review Details
05/24/2024 COMMERCIAL REVIEW - FULL v.1 05/24/2024 REQUIRES RESUBMIT Review Details
03/04/2024 COMMERCIAL REVIEW - FULL v.2 04/01/2024 APPROVED Review Details
02/21/2024 COMMERCIAL REVIEW - FULL v.1 02/21/2024 REQUIRES RESUBMIT Review Details
05/28/2024 COMMERCIAL REVIEW - FULL v.2 06/12/2024 APPROVED Review Details
11/27/2023 COMMERCIAL REVIEW - FULL v.1 02/05/2024 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Total Outstanding Activity Conditions - 17
Date Name
04/03/2024 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
04/03/2024 Masonry Inspection Report submittal review is required.
04/03/2024 Automatic Fire Sprinklers Designs must be submitted and approved prior to final.
04/03/2024 EFIS Designs must be submitted and approved prior to final.
04/03/2024 Fire Alams Designs must be submitted and approved prior to final.
04/03/2024 Metal Stairs Designs must be submitted and approved prior to final.
04/03/2024 Metal Stud Designs Designs must be submitted and approved prior to final.
04/03/2024 SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
04/03/2024 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
04/03/2024 WATER STERILIZATION REPORT IS REQUIRED.
11/20/2023 AIR BALANCING/COMMISSIONING REPORT IS REQUIRED.
11/22/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Conditions

Permit Number - T22CM01271
Permit Status: Issued
Permit Description: New Commercial Storage Facility
Date Description Comments
07/28/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
06/18/2024 Prior to Issuance: This project requires issuance of a Development Package (DP) permit prior to issuance of this permit. Prior to TCO/Final: This project requires full completion of a Development Package (DP) permit prior to Temporary C of O and/or final completion this permit.
11/20/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.

Outstanding Inspections

Permit Status: Issued
Permit Number: T22CM01271
Permite Description: New Commercial Storage Facility
Total Outstanding Inspections - 9
Last Inspection Date Description Inspector Results Comments
03/06/2024 COT - HCPL - Sewer N/A Partial Pass
03/08/2024 COT - HCBU - Stem Wall/Retaining Wall N/A Partial Pass Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape
Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans
3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed.
03/15/2024 COT - HCEL - Electrical Underground N/A Partial Pass
06/05/2024 COT - HCBU - Interior Shear Bracing N/A Partial Pass 6/5/24: x-bracing per plan at first floor ok to proceed
06/07/2024 COT - HCBU - Roof Nailing N/A Partial Pass 6/7/24: second floor decking fastened per schedule ok to proceed.
06/14/2024 COT - HCBU - Preslab N/A Partial Pass 6/13/24: Slab on deck 2nd floor Gridline A-B.5/1-7.3 reinforcement per plans.
6/14/24: slab on deck 2nd floor Gridline B.5-Z.3/1-17.3 reinforced per plans
10/01/2024 COT - FCON - Sprinkler - Final N/A Re-inspection required Looked at fire line under pressure. OK to bury. Still need flush. Waiting for permit to be issued.
10/23/2024 COT - HCBU - Building Progress N/A Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
8/7/24: DensGlass sheathing fastened per schedule first floor complete.
8/13/24: okay to cover galvanized roofing
9/24/24: first floor electrical in wall passed, first floor framing complete.
9/25/25: 2nd and 3rd floor framing at exterior walls per plan ok to proceed. 2nd floor electrical in wall at bathroom passed, plumbing at 2nd floor and first floor passed.
10/23/24: drywall nailing per plan at first floor sales area. Framing per plan at mechanical shaft at all three floors.
10/29/2024 COT - HCEL - Electrical Intermediate N/A Partial Pass

Completed Inspections

Permit Status: Issued
Permit Number: T22CM01271
Permit Description: New Commercial Storage Facility
Total Completed Inspections - 5
Date Description Inspector Results Comments
03/08/2024 COT - HCBU - Masonry Pregrout Passed Please remove any grade steaks, or rebar that is touching or embedded in the dirt or insulate with minimum 10 mil tape
Partial approval for footers, first floor, Elevator pit, and one set of stairs marked on plans
3/8/24: Stemwalls for stairway at southeast corner and northwest corner reinforcement per plan. Ok to proceed.
04/04/2024 COT - HCBU - Excavation/Rebar/Zoning Passed 4/4/24: Footer and second half of preslab ok to pour concrete.
07/02/2024 COT - HCBU - Framing Passed
10/08/2024 COT - HCPL - Yard Water Line Passed
10/29/2024 BULD - Electrical Clearance Passed Clearance for TEP ECO. 10/29/2024

Documents

File Name Document Type  
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
CONS-REV2_PLAN SET_V2.PDF DOCUMENTS VIEW
REV2_NARRATIVE_V2.PDF DOCUMENTS VIEW
CONS-REV2_PLAN SET_V2.PDF DOCUMENTS VIEW
REV2_NARRATIVE_V2.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
REV1_NARRATIVE_V2.PDF DOCUMENTS VIEW
REV1_PLAN SET_V2.PDF DOCUMENTS VIEW
CONS-STANTEC_REVISIONS_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_PLANS.PDF DOCUMENTS VIEW
CONS-STANTEC_REVISIONS_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
TUC_23_058_T22CM01271_CAP_BRIDGES_REVISIONS_APPROVED_CALCS_STRUCT_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_REVISIONS_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
REV1_1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_REVISIONS_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
REV1_1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
REV1_1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_REVISIONS_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
TUC_23_058_T22CM01271_CAP_BRIDGES_REVISIONS_APPROVED_CALCS_STRUCT_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT1_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT1_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_CALCS_STRUCT2_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_ENERGY_V1.PDF DOCUMENTS VIEW
STANTEC_APPROVED_SPECS_V1.PDF DOCUMENTS VIEW
STANTEC_SPEC_INSPEC_CERT1-2023-11-20_V1.PDF DOCUMENTS VIEW
STANTEC_SPEC_INSPEC_CERT2-2023-11-20_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
CONS-STANTEC_APPROVED_PLANS_V1.PDF DOCUMENTS VIEW
CONS-REV1_PLAN SET_V1.PDF DOCUMENTS VIEW
REV1_REVISION NARRATIVE_V1.PDF DOCUMENTS VIEW