Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM01271

Parcel: 13213113C

Inspection Status: Not Ready

Inspection History: COT - HCBU - Building Progress

Permit Number - T22CM01271

Inspection Description - COT - HCBU - Building Progress

Inspection Status - Not Ready

Date Description Inspector Results Comments
04/08/2024 COT - HCBU - Building Progress Not Ready
04/09/2024 COT - HCBU - Building Progress Not Ready
04/10/2024 COT - HCBU - Building Progress Partial Pass
04/12/2024 COT - HCBU - Building Progress Partial Pass
04/16/2024 COT - HCBU - Building Progress Partial Pass
04/17/2024 COT - HCBU - Building Progress Partial Pass
04/19/2024 COT - HCBU - Building Progress Not Ready
04/23/2024 COT - HCBU - Building Progress Partial Pass
04/25/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
04/29/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
05/02/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
05/06/2024 COT - HCBU - Building Progress Partial Pass
05/10/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
07/01/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
07/09/2024 COT - HCBU - Building Progress Partial Pass 7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
07/17/2024 COT - HCBU - Building Progress Not Ready Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
07/18/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
07/29/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
08/07/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
8/7/24: DensGlass sheathing fastened per schedule first floor complete.
08/13/2024 COT - HCBU - Building Progress Partial Pass 8/13/24: okay to cover galvanized roofing
09/24/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
8/7/24: DensGlass sheathing fastened per schedule first floor complete.
8/13/24: okay to cover galvanized roofing
9/24/24: first floor electrical in wall passed, first floor framing complete.
09/25/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
8/7/24: DensGlass sheathing fastened per schedule first floor complete.
8/13/24: okay to cover galvanized roofing
9/24/24: first floor electrical in wall passed, first floor framing complete.
9/25/25: 2nd and 3rd floor framing at exterior walls per plan ok to proceed. 2nd floor electrical in wall at bathroom passed, plumbing at 2nd floor and first floor passed.
10/23/2024 COT - HCBU - Building Progress Partial Pass Partial approval for two elevator shafts from floor elevation and two stairwell shaft first lift OK to grout
Partial approval for south stair tower, and two elevator towers
Partial approval for south stair tower 3rd lift
Partial approval for three towers third lift, north tower 2nd lift only
Partial approval for south three towers 4th lift and notch tower third lift ok to grout
4/25/24: partial approval for all four towers 5th lift ok to grout.
4/29/24: partial approval for all four towers 6th lift ok to grout @28'.
5/2/24:partial approval for all four towers 7th lift ok to grout @32'
5/6/24 partial approval from 32 to 36 feet. OK to grout on all four towers.
5/10/24: partial approval from 36' to 40'. Ok to grout on all four tower.
7/1/24: third floor decking fastened per schedule ok to proceed.
7/9/2024: partial pass. Concrete Reinforcement 3rd Floor. Okay for concrete placement.
7/17/24: not ready
7/18/24: DensGlass sheathing fastened per schedule 0'-4' on (North, East, South, West) . Ok to proceed
7/29/24: Electrical underground from transformer on south east corner of building to building equipment. (2)4" conduit per plan ok to backfill.
8/7/24: DensGlass sheathing fastened per schedule first floor complete.
8/13/24: okay to cover galvanized roofing
9/24/24: first floor electrical in wall passed, first floor framing complete.
9/25/25: 2nd and 3rd floor framing at exterior walls per plan ok to proceed. 2nd floor electrical in wall at bathroom passed, plumbing at 2nd floor and first floor passed.
10/23/24: drywall nailing per plan at first floor sales area. Framing per plan at mechanical shaft at all three floors.