Permit: T22CM01222
Permit Details
Apply Date:
02/17/2022
Applicant:
Solon Corporation
Description:
325kW AC Photovoltaic Parking Canopy Installation
Contractors:
- Solon Corporation
Permit Reviews
Permit Number - T22CM01222
Permit Status: L of c
Permit Description: 325kW AC Photovoltaic Parking Canopy Installation
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/17/2022 | COMMERCIAL - TI | 04/26/2022 | COMPLETED |
Completed Inspections
Permit Status: L of c
Permit Number: T22CM01222
Permit Description: 325kW AC Photovoltaic Parking Canopy Installation
Total Completed Inspections - 13
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/16/2022 | ELECTRIC - UFER | DMUNIZ | Approved | Approved, structural steel depth for each column meets electrode conductor requirements. |
05/16/2022 | EXCAVATION/LAYOUT REBAR & ZON | DMUNIZ | Approved | Approved, columns set for canopy A,B,C,D all ok for concrete placement. |
06/08/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Approved to the gear rack equipment location at the building, okay to backfill progress areas |
06/08/2022 | ELECTRIC - UNDERGROUND | TGAUSP | Approved | Partial continued from end of the previous inspection to the gear rack equipment location at the building, okay to backfill progress areas |
07/05/2022 | ELECTRIC - OUTDOOR LIGHTING | TGAUSP | Approved | Approved |
07/05/2022 | ELECTRIC - INTERMEDIATE | TGAUSP | Approved | Approved |
07/05/2022 | BUILDING - PROGRESS | TGAUSP | Approved | Approved |
07/05/2022 | FRAMING | TGAUSP | Approved | Approved per Special Inspection |
07/10/2022 | ELECTRIC - RECONNECT | DMUNIZ1 | Approved | After Hours Inspection for PV Interconnection, verbal clearance sent to TEP for RECN/DGL. |
07/28/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE DGC |
07/28/2022 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | Ap Clear dgc |
07/28/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap |
07/28/2022 | BUILDING - FINAL | DQUINN | Approved | Ap |