Permit: T22CM01094
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
9921 E POTOMAC PL
Address NEW:
9921 E POTOMAC PL
Apply Date:
02/14/2022
Applicant:
William Burris
Description:
Sleeping Quarters Addition & Renovate Carport to Garage
Permit Reviews
Permit Number - T22CM01094
Permit Status: Complete
Permit Description: Sleeping Quarters Addition & Renovate Carport to Garage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/14/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/23/2022 | COMPLETED |
| 03/31/2022 | RESUBMITTAL | 04/06/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM01094
Permite Description: Sleeping Quarters Addition & Renovate Carport to Garage
Total Outstanding Inspections - 7
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/06/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | {Activity date: 04/06/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 04/06/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 04/06/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 10/19/2022 | COT - RSPL - Yard Water Line | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NA} |
| 10/19/2022 | COT - RSPL - Gas Pressure Test | N/A | Canceled | {Activity date: 10/19/2022; Status: Not Applicable; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NA} |
| 10/26/2022 | COT - RSEL - Grounding/Bonding | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
| 10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM01094
Permit Description: Sleeping Quarters Addition & Renovate Carport to Garage
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2022 | COT - RSBU - Preslab | Passed | {Activity date: 06/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 06/08/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NR} | |
| 06/24/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/24/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -AP. Including Ufer and 2” clean out.} | |
| 07/18/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 07/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 07/18/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 07/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 08/09/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/09/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 06/13/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. OK to cover and backfill; still need cleanout within five feet of exterior and tracer on two inch line. } ; {Activity date: 06/08/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -DE. 1-Install clean out within five feet of exterior. 2-Connect to Building sewer. 3-Install tracer wire. } |
|
| 08/19/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/12/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Denied: 1- missing fire-blocking at all dropped ceilings. 2-Wire missing from front box.} ; {Activity date: 08/09/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Not ready.} | |
| 08/19/2022 | COT - LCBU - Framing | Passed | {Activity date: 08/19/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/12/2022; Status: Denied; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Denied: See 1080 notes.} ; {Activity date: 08/09/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -Not ready.} | |
| 09/23/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - CODE INCR/CUTOVER} | |
| 09/23/2022 | COT - RSEL - Electrical Underground | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay to backfill progress areas} | |
| 09/23/2022 | COT - RSEL - Service Upgrade | Passed | {Activity date: 09/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Approved, please send INCR Clearance to TEP for the electrical cutover at new location} | |
| 10/19/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 10/19/2022 | COT - RSEL - Outdoor Lighting | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} | |
| 11/08/2022 | COT - RSEL - Grounding/Bonding | Passed | ||
| 11/08/2022 | COT - RSPL - Plumbing Final | Passed | ||
| 11/08/2022 | COT - RSEL - Electrical Final | Passed |