Inspection Status: Passed
Inspection History: COT - RSPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 08/09/2022 |
COT - RSPL - Rough Soil |
RCHANDLER |
Approved |
Entered by NGARCIA3 - Approved |
| 06/13/2022 |
COT - RSPL - Rough Soil |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - PA. OK to cover and backfill; still need cleanout within five feet of exterior and tracer on two inch line.
|
| 06/08/2022 |
COT - RSPL - Rough Soil |
RCHANDLER |
Denied |
Entered by VVERA1 - -DE. 1-Install clean out within five feet of exterior. 2-Connect to Building sewer. 3-Install tracer wire.
|