Permit: T22CM00966
Permit Details
Status:
Complete
Type:
Residential Building - One or Two Family
Address:
8072 E MI CASITA ST
Address NEW:
8072 E MI CASITA ST
Apply Date:
02/08/2022
Applicant:
Description:
STORAGE BUILDING
Permit Reviews
Permit Number - T22CM00966
Permit Status: Complete
Permit Description: STORAGE BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/08/2022 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 03/23/2022 | COMPLETED |
| 07/18/2022 | REVISION - - 1ST | 07/22/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM00966
Permite Description: STORAGE BUILDING
Total Outstanding Inspections - 4
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2022 | RSME - Mechanical Progress | N/A | Canceled | {Activity date: 07/20/2022; Status: Not Applicable; Inspector: KEN; Comment: Entered by KKARSEN1 - } |
| 05/15/2023 | COT - RSEL - Electrical Underground | N/A | Not Applicable | 5-15-24: Feeders run overhead. |
| 08/07/2023 | COT - RSEL - Electrical Final | N/A | Canceled | |
| 12/20/2022 | RSBU - Building Final | N/A | Re-inspection required | Need landings at all Man-doors. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM00966
Permit Description: STORAGE BUILDING
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/12/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 08/12/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 08/26/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 08/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 08/26/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - Approved} | |
| 12/27/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 12/27/2022 | COT - RSBU - Roof Nailing | Passed | ||
| 05/03/2023 | COT - RSPL - Yard Water Line | Passed | ||
| 05/09/2023 | COT - RSPL - Plumbing Final | Passed | ||
| 05/17/2023 | COT - LCBU - Framing | Passed | ||
| 08/29/2023 | COT - RSME - Mechanical Final | Passed | ||
| 12/06/2023 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 12/20/2023 | COT - RSEL - Electrical Final | Passed | 12/20/23: GFCI outlets have been installed within 6' of any water source. Water heater T & P valve has been routed to the exterior of house. Electrical panel is properly labeled. A disconnect has been installed in water heater closet in place of the breaker lockout. Project is complete. Okay to issue Certificate of Occupancy for project. | |
| 12/20/2023 | RSBU - Building Final | Passed | 12/20/23: GFCI outlets have been installed within 6' of any water source. Water heater T & P valve has been routed to the exterior of house. Electrical panel is properly labeled. A disconnect has been installed in water heater closet in place of the breaker lockout. Project is complete. Okay to issue Certificate of Occupancy for project. |