Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
3115 N FAIRVIEW AV
Apply Date:
02/07/2022
Applicant:
Christopher Perry
Description:
Demo existing outdated electrical disconnects and transformers in electrical yard. Replace with new

Permit Reviews

Permit Number - T22CM00921
Permit Status: Complete
Permit Description: Demo existing outdated electrical disconnects and transformers in electrical yard. Replace with new
Start Date Submittal Complete Date Status  
02/07/2022 OTHER 03/08/2022 COMPLETED Review Details
03/25/2022 RESUBMITTAL 03/30/2022 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: T22CM00921
Permit Description: Demo existing outdated electrical disconnects and transformers in electrical yard. Replace with new
Total Completed Inspections - 5
Date Description Inspector Results Comments
05/23/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 05/23/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by VVERA1 - Ap - rods

}
05/24/2022 COT - LCEL - Electrical Underground Passed {Activity date: 05/24/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap
Last 10’ of 2” from J2 to new trans ok.
Under ground complete.
} ; {Activity date: 05/23/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
290’ total of 2” from Trans 2 to J3#3 and from T5 to J3#3} ; {Activity date: 05/20/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
2” and 4” from trans 4 to J2#3 ok to backfill.} ; {Activity date: 05/19/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
50’ of 4” out of trans 4 to the west, and 15’ to complete main entry riser.
Ok to backfill.

} ; {Activity date: 05/18/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
50 ‘ of 3 - 4” conduit, from switch gear to south of manhole.
80’ - 4” from trans #4 to Covington rd intersection, all ok to backfill.} ; {Activity date: 05/17/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - PARTIAL: FOR THE 4” CONDUIT CONTINUING FROM J2 #2 CABINET HEADING WEST 220’ TOWARDS J2 #3 CABINET AND ENDING AT THE COVINGTON INTERSECTION, OKAY TO BACKFILL PROGRESS AREAS} ; {Activity date: 05/16/2022; Status: Cancelled; Inspector: DQUINN; Comment: Entered by RSALDAT1 - ca
Per Pat

} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
10’ to and from next lateral J2 cab and 20’ further down main trench ok to backfill.

} ; {Activity date: 05/12/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Partial approval 4” CONTINUES WEST 80’ TOWARDS J2 CABINET

} ; {Activity date: 05/11/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
From last stop, 2” goes 20’ to 90 degree left for 10’ to the C phase box, and the 4” continues west for 70’, towards the next J2 cab. Ok to backfill.} ; {Activity date: 05/10/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for 4” primary and 2” secondary from the intersection of Northridge and Westminster heading west to transformer T-3, okay to backfill progress areas

} ; {Activity date: 05/09/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
4” and 2” from main trench to J2 cab, then back to main trench and west another 70’ - ok to backfill.

} ; {Activity date: 05/06/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by NGARCIA3 - pa
Ok to backfill 110’ from Devonshire intersection, west to 90 degree turn south towards J2 cab, containing 1 -4” and 1 -2” conduit.} ; {Activity date: 05/05/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for the 4” and 2” conduit for primary and T-1 transformer lines, starting at the main intersection heading west approx 200’, okay to backfill progress areas

}
04/25/2023 COT - LCEL - Electrical Intermediate Passed New switch gear, line side and power side. Power kill by TEP, recalled TEP to energize system at 1140 hours.
09/27/2023 COT - LCEL - Service Upgrade Passed
09/27/2023 COT - LCEL - Electrical Final Passed

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW