Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
01/28/2022
Applicant:
Description:
NEW SFR MODEL RICHT914 T19-M0082

Outstanding Activity Conditions

Permit Number - T22CM00691
Permit Status: Issued
Permit Description: NEW SFR MODEL RICHT914 T19-M0082
Total Outstanding Activity Conditions - 2
Date Name
01/28/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
01/28/2022 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)

Completed Inspections

Permit Status: Issued
Permit Number: T22CM00691
Permit Description: NEW SFR MODEL RICHT914 T19-M0082
Total Completed Inspections - 23
Date Description Inspector Results Comments
02/23/2022 COT - RSPL - Yard Water Line Passed {Activity date: 02/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
02/23/2022 COT - RSPL - Sewer Passed {Activity date: 02/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
02/23/2022 COT - RSPL - Rough Soil Passed {Activity date: 02/23/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/10/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 03/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/10/2022 COT - RSBU - Preslab Passed {Activity date: 03/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/10/2022 COT - RSEL - Electrical Underground Passed {Activity date: 03/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/10/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 03/10/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/24/2022 COT - RSBU - Roof Nailing Passed {Activity date: 03/24/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
03/31/2022 COT - LCBU - Framing Passed {Activity date: 03/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
03/31/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 03/31/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 03/30/2022; Status: Cancelled; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CA no plans on site} ; {Activity date: 03/24/2022; Status: Correction Required; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CO
1. Missing several anchor bolts at shear walls
2. Framing at patio door opening not per plan
3. HD at rear shear wall not nailed off}
09/15/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 09/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE ECO}
09/15/2022 COT - RSEL - Construction Power Passed {Activity date: 09/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP. TEP ECO}
09/15/2022 RSPL - Plumbing Progress Passed {Activity date: 09/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/15/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 09/15/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
09/30/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 09/30/2022; Status: Approved; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - approved} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR}
10/04/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/30/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. 10’ clearance fresh air intake} ; {Activity date: 09/15/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - DE
1. Vents are dry
2. Fresh air intake is within 10 feet of a vent
3. Block and seal AC chase at floor and ceiling
4. Water test tubs and showers
5. Maintain min 1 inch clearance from B-vent to combustibles
6. Reinforce top plate at B-vent & block all holes}
10/04/2022 RSME - Mechanical Progress Passed {Activity date: 10/04/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 09/30/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - not ready provide 10’ clearance fresh air intake from vent lines .} ; {Activity date: 09/15/2022; Status: Not ready for Inspection; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - NR}
10/20/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 10/20/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 10/17/2022; Status: Not ready for Inspection; Inspector: SCARRAZCO; Comment: Entered by VVERA1 - Not ready. Missing edge metal around windows and closet. Loose edge metals and incomplete.}
11/23/2022 COT - RSEL - Outdoor Lighting Passed
11/29/2022 COT - RSME - Mechanical Final Passed
11/29/2022 COT - RSPL - Plumbing Final Passed
11/30/2022 COT - RSEL - Electrical Final Passed corrections were made
11/30/2022 RSBU - Building Final Passed corrections were made

Documents

File Name Document Type  
APPLICATION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
SITE PLAN.PDF DOCUMENTS VIEW