Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Permit Details
Status:
Final
Type:
Barricade and Excavation
Apply Date:
01/26/2021
Applicant:
COX COMMUNICATIONS
Description:
Change from aerial to underground work: From the TEP Pole SW corner of 410 W Simmons Rd, riser and begin 90 trench/bore, placing 2-2''conduit and 625' coax cable heading Southwest to out of ROW
Simmons Rd is under a pavement cut moratorium until September 18, 2023 and additional pavement repairs must be performed if the pavement is cut. A 2" mill and inlay, with PAG #2 (406 Asphaltic Concrete replacement specification, dated 12/18/19) will be required for the entire width of the impacted lanes and extend 50' on each side of the trench.