Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Commercial Building
Address NEW:
1840 W VALENCIA RD
Apply Date:
12/27/2021
Applicant:
Description:
INTERIOR TENANT ALTERATION OF EXISTING TENANT SPACE

Permit Reviews

Permit Number - T21CM09881
Permit Status: Issued
Permit Description: INTERIOR TENANT ALTERATION OF EXISTING TENANT SPACE
Start Date Submittal Complete Date Status  
02/15/2022 RESUBMITTAL 02/23/2022 COMPLETED Review Details
03/01/2022 RESUBMITTAL 03/07/2022 COMPLETED Review Details
12/27/2021 COMMERCIAL - BLDG/FIRE/ZONING/ENG 02/09/2022 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T21CM09881
Permit Status: Issued
Permit Description: INTERIOR TENANT ALTERATION OF EXISTING TENANT SPACE
Total Outstanding Activity Conditions - 4
Date Name
03/04/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
03/04/2022 SHOP DRAWINGS REQUIRED FOR SPRINKLER.
03/04/2022 SHOP DRAWINGS REQUIRED FOR FIRE ALARM.
03/04/2022 SHOP DRAWINGS REQUIRED FOR SIGNAGE.

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM09881
Permite Description: INTERIOR TENANT ALTERATION OF EXISTING TENANT SPACE
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
10/26/2022 COT - LCPL - Plumbing Progress N/A Not Ready

Completed Inspections

Permit Status: Issued
Permit Number: T21CM09881
Permit Description: INTERIOR TENANT ALTERATION OF EXISTING TENANT SPACE
Total Completed Inspections - 19
Date Description Inspector Results Comments
05/10/2022 COT - LCEL - Electrical Underground Passed {Activity date: 05/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay for concrete placement}
05/10/2022 COT - LCBU - Preslab Passed {Activity date: 05/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved, okay for concrete placement}
05/13/2022 COT - LCEL - Electrical Intermediate Passed {Activity date: 05/13/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/12/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - - Partial, okay to cover progress areas without plumbing} ; {Activity date: 05/11/2022; Status: Denied; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Denied. No messages, no contractor listed. Contacted owner, left a message. Please contact your inspector for further information.}
05/17/2022 COT - LCBU - Framing Passed {Activity date: 05/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial pending intermediates, okay to cover progress areas without plumbing} ; {Activity date: 05/12/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - Partial, pending intermediates

} ; {Activity date: 05/11/2022; Status: Denied; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Denied. No messages, no contractor listed. Contacted owner, left a message. Please contact your inspector for further information.}
05/17/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 05/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/16/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - NR, cancelled by Contractor} ; {Activity date: 05/13/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR, water and DWV not on test
}
05/17/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 05/17/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for front sales area}
06/02/2022 COT - LCBU - Building Above Ceiling Passed {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
06/02/2022 COT - LCME - Mechanical Progress Passed {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/27/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - PARTIAL for mechanical above hard lid areas, okay to cover}
06/02/2022 COT - LCPL - Plumbing Above Ceiling Passed {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/27/2022; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by VVERA1 - CA}
06/02/2022 COT - LCEL - Electrical Above Ceiling Passed {Activity date: 06/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/27/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - PARTIAL for electrical above hard lid areas, okay to cover}
06/16/2022 COT - LCEL - Electrical Final Passed {Activity date: 06/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved}
06/16/2022 COT - FCON - Fire - Final Passed {Activity date: 06/16/2022; Status: Approved; Inspector: wmotto; Comment: Entered by WMOTTO1 - } ; {Activity date: 06/15/2022; Status: Cancelled; Inspector: YM; Comment: Entered by YMONTIJ1 - RE-OPEN PERMIT}
06/22/2022 COT - LCME - Mechanical Final Passed {Activity date: 06/22/2022; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED} ; {Activity date: 06/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, pending Air Balance Report} ; {Activity date: 06/08/2022; Status: Partial Approval; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF AIR BALANCE REPORT COMPLETED}
07/13/2022 COT - LCBU - Building Final Passed {Activity date: 07/13/2022; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - } ; {Activity date: 06/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, pending plumbing and mechanical, TCO request to start partially stock.

} ; {Activity date: 06/15/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR, cancelled by Contractor} ; {Activity date: 06/13/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by VVERA1 - NR}
07/13/2022 COT - LCPL - Plumbing Final Passed {Activity date: 07/13/2022; Status: Approved; Inspector: RSHERRY; Comment: Entered by RSHERRY1 - REVIEW OF THE WATER DISINFECTION REPORT COMPLETED} ; {Activity date: 06/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial, pending Chlorination Report} ; {Activity date: 03/04/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION}
09/20/2022 COT - LCEL - Electrical Progress Passed {Activity date: 09/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - }
09/20/2022 COT - LCME - Mechanical Intermediate Passed {Activity date: 09/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - }
09/20/2022 COT - LCEL - Service Upgrade Passed {Activity date: 09/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - }
09/20/2022 COT - LCBU - Building Progress Passed {Activity date: 09/20/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - }

Documents

File Name Document Type  
T21CM09881 AIR BALANCE1.PDF DOCUMENTS VIEW
T21CM09881 WATER REPORT1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
DATA SHEET.PDF DOCUMENTS VIEW
PLAN SET.PDF CONSTRPLANS VIEW