Permit: T21CM09674
Permit Details
Apply Date:
12/17/2021
Applicant:
Description:
Interior remodel of an existing convenience store to add and relocate food equipment.
Permit Reviews
Permit Number - T21CM09674
Permit Status: Complete
Permit Description: Interior remodel of an existing convenience store to add and relocate food equipment.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/23/2022 | RESUBMITTAL | 04/27/2022 | COMPLETED |
| 12/17/2021 | COMMERCIAL - TI | 01/14/2022 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09674
Permite Description: Interior remodel of an existing convenience store to add and relocate food equipment.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2022 | COT - LCEL - Electrical Intermediate | N/A | Partial Pass | partial approval for relocation of coffee bar to new location |
| 12/02/2022 | COT - LCBU - Framing | N/A | Partial Pass | 75 feet of yard water line on West side. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09674
Permit Description: Interior remodel of an existing convenience store to add and relocate food equipment.
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/22/2022 | COT - LCEL - Electrical Intermediate | Passed | In wall electric. Ok to cover walls. | |
| 11/29/2022 | COT - LCEL - Electrical Above Ceiling | Passed | Feeders and conduits to Panel K. | |
| 12/02/2022 | COT - LCBU - Framing | Passed | Drywall nailing. | |
| 12/12/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 05/16/2023 | COT - LCPL - Rough Soil | Passed | ||
| 05/16/2023 | COT - LCPL - Plumbing Final | Passed | ||
| 05/16/2023 | COT - LCME - Mechanical Final | Passed | ||
| 05/16/2023 | COT - LCME - Mechanical Intermediate | Passed | ||
| 05/16/2023 | COT - FCON - Fire - Final | Passed | ||
| 05/16/2023 | COT - LCBU - Building Above Ceiling | Passed | ||
| 05/16/2023 | COT - LCBU - Building Progress | Passed | ||
| 05/16/2023 | COT - LCEL - Electrical Final | Passed | ||
| 05/16/2023 | COT - LCBU - Building Final | Passed | ||
| 05/16/2023 | COT - ENGR - Site - Assurance Release | Passed | ||
| 05/16/2023 | BULD - Electrical Clearance | Passed |