Permit Details

Status:
Complete
Type:
Commercial Building
Address NEW:
2960 N CAMPBELL AV
Apply Date:
12/08/2021
Applicant:
Description:
L of C - New Commercial Shell

Permit Reviews

Permit Number - T21CM09423
Permit Status: Complete
Permit Description: L of C - New Commercial Shell
Start Date Submittal Complete Date Status  
02/25/2022 RESUBMITTAL 03/25/2022 COMPLETED Review Details
03/25/2022 RESUBMITTAL 04/13/2022 COMPLETED Review Details
05/27/2022 REVISION - - 1ST 06/02/2022 COMPLETED Review Details
06/10/2022 REVISION - - 2ND 06/21/2022 COMPLETED Review Details
07/06/2022 REVISION - - 3RD 07/06/2022 ACTIVE Review Details
12/08/2021 COMMERCIAL - NEW 02/02/2022 COMPLETED Review Details
05/18/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/22/2023 APPROVED Review Details
04/14/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 04/14/2023 APPROVED Review Details
01/10/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/30/2023 APPROVED Review Details

Conditions

Permit Number - T21CM09423
Permit Status: Complete
Permit Description: L of C - New Commercial Shell
Date Description Comments
12/15/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
12/15/2021 ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I)
12/15/2021 SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY.
12/15/2021 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
12/15/2021 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
12/15/2021 SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED.
12/17/2021 SPECIAL INSPECTION REQUIRED FOR OUTDOOR LIGHTING

Outstanding Inspections

Permit Status: Complete
Permit Number: T21CM09423
Permite Description: L of C - New Commercial Shell
Total Outstanding Inspections - 12
Last Inspection Date Description Inspector Results Comments
10/27/2022 COT - LCBU - Framing N/A Not Ready
10/26/2022 COT - LCBU - Masonry Pregrout N/A Not Ready
10/26/2022 COT - LCBU - Preslab N/A Not Ready
10/26/2022 COT - LCPL - Rough Soil N/A Not Ready
12/30/2022 COT - LCPL - Gas Pressure Test N/A Not Applicable shell only
12/30/2022 COT - LCBU - Building Above Ceiling N/A Not Applicable n/a
12/30/2022 COT - LCPL - Plumbing Final N/A Not Ready
02/10/2023 COT - BULD - SWG Clearance N/A Not Applicable shell only
COT - FCON - Fire - Final N/A Not Ready No power to building
12/30/2022 COT - LCPL - Plumbing Roof Drains N/A Not Ready
03/06/2023 COT - LCEL - Outdoor Lighting N/A Not Ready
03/06/2023 COT - LCEL - Electrical Final N/A Not Ready

Completed Inspections

Permit Status: Complete
Permit Number: T21CM09423
Permit Description: L of C - New Commercial Shell
Total Completed Inspections - 32
Date Description Inspector Results Comments
04/21/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 04/21/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - CODE TMPP}
04/21/2022 COT - LCEL - Construction Power Passed {Activity date: 04/21/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap

Clear temp power}
04/21/2022 COT - LCEL - Temporary Service Passed {Activity date: 04/21/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap}
05/17/2022 COT - LCBU - Excavation/Rebar/Zoning Passed {Activity date: 05/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap

Wall and column footings complete for building and ok to pour.} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
South and east elevations ok to pour.
}
05/17/2022 COT - LCEL - Grounding/Bonding Passed {Activity date: 05/17/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap} ; {Activity date: 05/13/2022; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by VVERA1 - pa
Ufer for SES ok}
05/24/2022 COT - LCBU - Stem Wall/Retaining Wall Passed {Activity date: 05/24/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap
Entire perimeter stem ok to grout.}
08/08/2022 COT - LCBU - Roof Nailing Passed {Activity date: 08/08/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved} ; {Activity date: 08/04/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval for north suite only} ; {Activity date: 08/03/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Inspection canceled by contractor

}
08/09/2022 COT - LCPL - Yard Water Line Passed {Activity date: 08/09/2022; Status: Approved; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/03/2022; Status: Approved; Inspector: DQUINN; Comment: Entered by NGARCIA3 - Ap
2 - 2" pvc lines
Ok to backfill.}
09/16/2022 COT - LCEL - Electrical Underground Passed {Activity date: 09/16/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - Approved}
11/08/2022 COT - LCBU - Framing Passed for shell only
11/08/2022 COT - LCBU - Masonry Pregrout Passed no inspection performed, inspections were conducted by third party please submit approvals through permit portal
12/22/2022 COT - HCBU - Exterior Clips/Sheathing Passed
03/03/2023 COT - LCEL - Electrical Progress Passed
03/03/2023 COT - LCEL - Electrical Above Ceiling Passed approved for shell only
12/30/2022 COT - LCPL - Sewer Passed inspected by E. Stevens: Contact is Duff 520-405-7581
12/30/2022 COT - LCBU - Building Final Passed
12/30/2022 COT - LCME - Mechanical Intermediate Passed
12/30/2022 COT - LCBU - Building Progress Passed
12/30/2022 COT - LCPL - Plumbing Intermediate Passed shell only
12/30/2022 COT - LCME - Mechanical Final Passed shell only
12/30/2022 COT - FCON - Underground Flush Passed approved by C Gates on 9/14/2022
12/30/2022 COT - FCON - Underground Pressure Passed Approved by C Gates on 9/14/2022
12/30/2022 COT - LCBU - Sustainability Passed n/a
01/11/2023 COT - LCEL - Electrical Intermediate Passed
01/11/2023 BULD - Electrical Clearance Passed One meter for house panel.
02/02/2023 FCON – OH Piping & Hydro Passed
02/10/2023 COT - LCPL - Plumbing Final Passed shell only
02/14/2023 COT - FCON - Fire - Final Passed shell only
02/14/2023 COT - FCON - Sprinkler - Final Passed shell only
02/14/2023 COT - FCON - Alarm - Final Passed shell only
02/28/2023 COT - LCPL - Plumbing Roof Drains Passed
03/07/2023 COT - LCEL - Electrical Final Passed shell only

Documents

File Name Document Type  
APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GCL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
GEOTECH REPORT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
PROJECT MANUAL 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV1_PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_JOB CARD 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_PERMIT 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_PLAN SET 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REV2_REVISION NARRATIVE 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION LETTER 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
REVISION1 APPLICATION 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
SIC 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
STRUC CALCS 2024 MASS-UPLOAD.PDF DOCUMENTS VIEW
LOFC_LETTEROFCOMPLETION.PDF DOCUMENTS VIEW
FINAL SIC OUTDOOR LIGHTING-2023-05-16_V1.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GCL.PDF DOCUMENTS VIEW
GEOTECH REPORT.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
PROJECT MANUAL.PDF DOCUMENTS VIEW
REV1_JOB CARD.PDF DOCUMENTS VIEW
REV1_PERMIT.PDF DOCUMENTS VIEW
REV1_PLAN SET.PDF DOCUMENTS VIEW
REV2_JOB CARD.PDF DOCUMENTS VIEW
REV2_PERMIT.PDF DOCUMENTS VIEW
REV2_PLAN SET.PDF DOCUMENTS VIEW
REV2_REVISION NARRATIVE.PDF DOCUMENTS VIEW
REVISION APPLICATION.PDF DOCUMENTS VIEW
REVISION LETTER.PDF DOCUMENTS VIEW
REVISION1 APPLICATION.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
STRUC CALCS.PDF DOCUMENTS VIEW
FINAL SIC-2023-04-11_V1.PDF DOCUMENTS VIEW
REV 3_ TRUSS CALCS (2).PDF DOCUMENTS VIEW
REV3_ ROOF TRUSSES_PKA REVIEWED.PDF DOCUMENTS VIEW