Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - LCBU - Masonry Pregrout
Permit Number - T21CM09423
Inspection Description - COT - LCBU - Masonry Pregrout
Inspection Status - Not Ready
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - LCBU - Masonry Pregrout | Not Ready | ||
| 07/14/2022 | COT - LCBU - Masonry Pregrout | DQUINN | Partial Approval | Entered by NGARCIA3 - pa GLs 5/A.9 - D.5, H/2 - 5, 2/D - E.5 - top out 20 to 24’ ok to grout. |
| 07/11/2022 | COT - LCBU - Masonry Pregrout | JBURGE | Partial Approval | Entered by VVERA1 - Partial. CMU walls at 16’ - 20’ on GL: 2/H - E; 5/H - E. Ok to place grout in progress areas. |
| 07/07/2022 | COT - LCBU - Masonry Pregrout | RCHANDLER | Partial Approval | Entered by NGARCIA3 - PA. 4th lift of Southwest walls at flower. |
| 06/27/2022 | COT - LCBU - Masonry Pregrout | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. 4th lift, west side wall, 12 to 16 feet. |
| 06/17/2022 | COT - LCBU - Masonry Pregrout | ESTEVENS | Partial Approval | Entered by NGARCIA3 - Partial. Ok to grout 3rd lift. |
| 06/15/2022 | COT - LCBU - Masonry Pregrout | ESTEVENS | Partial Approval | Entered by VVERA1 - Partial. Ok to grout second lift. |
| 05/26/2022 | COT - LCBU - Masonry Pregrout | DQUINN | Partial Approval | Entered by VVERA1 - pa Ok to grout 1st lift of all perimeter shell walls. |
| 05/24/2022 | COT - LCBU - Masonry Pregrout | DQUINN | Partial Approval | Entered by NGARCIA3 - pa Stem ok |
| 11/08/2022 | COT - LCBU - Masonry Pregrout | Passed | no inspection performed, inspections were conducted by third party please submit approvals through permit portal |