Inspection Status: Not Ready
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCBU - Masonry Pregrout |
|
Not Ready |
|
| 07/14/2022 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
GLs 5/A.9 - D.5, H/2 - 5, 2/D - E.5 - top out 20 to 24’ ok to grout. |
| 07/11/2022 |
COT - LCBU - Masonry Pregrout |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. CMU walls at 16’ - 20’ on GL: 2/H - E; 5/H - E. Ok to place grout in progress areas. |
| 07/07/2022 |
COT - LCBU - Masonry Pregrout |
RCHANDLER |
Partial Approval |
Entered by NGARCIA3 - PA. 4th lift of Southwest walls at flower. |
| 06/27/2022 |
COT - LCBU - Masonry Pregrout |
ESTEVENS |
Partial Approval |
Entered by VVERA1 - Partial. 4th lift, west side wall, 12 to 16 feet.
|
| 06/17/2022 |
COT - LCBU - Masonry Pregrout |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Ok to grout 3rd lift. |
| 06/15/2022 |
COT - LCBU - Masonry Pregrout |
ESTEVENS |
Partial Approval |
Entered by VVERA1 - Partial. Ok to grout second lift. |
| 05/26/2022 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by VVERA1 - pa
Ok to grout 1st lift of all perimeter shell walls. |
| 05/24/2022 |
COT - LCBU - Masonry Pregrout |
DQUINN |
Partial Approval |
Entered by NGARCIA3 - pa
Stem ok |
| 11/08/2022 |
COT - LCBU - Masonry Pregrout |
|
Passed |
no inspection performed, inspections were conducted by third party please submit approvals through permit portal |