Permit: T21CM09399
Permit Details
Apply Date:
12/07/2021
Applicant:
Description:
New Commercial Shell Bldg
Permit Reviews
Permit Number - T21CM09399
Permit Status: Complete
Permit Description: New Commercial Shell Bldg
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/23/2022 | REVISION - - 1ST | 06/29/2022 | COMPLETED |
12/07/2021 | 3RD PARTY REVIEW - COMMERCIAL | 02/04/2022 | COMPLETED |
Conditions
Permit Number - T21CM09399
Permit Status: Complete
Permit Description: New Commercial Shell Bldg
Date | Description | Comments |
---|---|---|
01/25/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
01/25/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
01/25/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
01/25/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
01/25/2022 | SHOP DRAWINGS REQUIRED FOR WOOD "I" JOISTS. | |
01/25/2022 | SPECIAL INSPECTION IS REQUIRED FOR EARTHWORK. | |
01/25/2022 | SPECIAL INSPECTION IS REQUIRED FOR EIFS. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM09399
Permite Description: New Commercial Shell Bldg
Total Outstanding Inspections - 3
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/07/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Canceled | {Activity date: 07/07/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - - Not Applicable.} |
07/07/2022 | COT - LCPL - Medical Gas Preconstruction Mtg | N/A | Canceled | {Activity date: 07/07/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - - Not Applicable.} |
07/07/2022 | COT - LCPL - Medical Gas/Test | N/A | Canceled | {Activity date: 07/07/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - - Not Applicable.} |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM09399
Permit Description: New Commercial Shell Bldg
Total Completed Inspections - 37
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/23/2022 | COT - LCEL - Grounding/Bonding | Passed | {Activity date: 03/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved Shop 16} | |
04/05/2022 | COT - LCBU - Stem Wall/Retaining Wall | Passed | {Activity date: 04/05/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} | |
04/26/2022 | COT - LCBU - Masonry Pregrout | Passed | {Activity date: 04/26/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for the 5th lift (top of wall) for the 3 masonry walls} ; {Activity date: 04/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, N,S,W CMU walls for shop 16 topped out and ok to grout.} ; {Activity date: 04/21/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial - 4th lift (20’) for the 3 masonry walls} ; {Activity date: 04/14/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial - 3rd lift (15’) for the 3 masonry walls} ; {Activity date: 04/12/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial - 2nd lift (10’) for the 3 masonry walls} ; {Activity date: 04/08/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial - 1st lift for the 3 masonry walls} ; {Activity date: 04/05/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for stem wall at north, east and west} | |
05/04/2022 | COT - LCPL - Rough Soil | Passed | {Activity date: 05/04/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved for waste and grease, connected to existing main, okay to backfill progress areas} | |
05/18/2022 | COT - LCBU - Preslab | Passed | {Activity date: 05/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
05/18/2022 | COT - LCPL - Yard Water Line | Passed | {Activity date: 05/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved 2” water from meter to building, okay to backfill progress areas} | |
05/23/2022 | COT - LCEL - Electrical Underground | Passed | {Activity date: 05/23/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved for electrical lines from property line to building, okay to backfill } ; {Activity date: 04/07/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for conduits starting at the SES location going along north wall and east walls to interior panels, okay to backfill} |
|
06/07/2022 | COT - LCBU - Excavation/Rebar/Zoning | Passed | {Activity date: 06/07/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/27/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for Trash Enclosure, okay for concrete placement} ; {Activity date: 03/31/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for building #16 column footings, okay to place concrete} ; {Activity date: 03/23/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - - Partial for Shop 16 building foundation on East, West and South walls, okay to pour} | |
06/08/2022 | COT - LCBU - Exterior Clips/Sheathing | Passed | {Activity date: 06/08/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
06/08/2022 | COT - LCBU - Roof Nailing | Passed | {Activity date: 06/08/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
06/10/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -AP. Rough in for boxes in walls. } |
|
06/10/2022 | COT - LCPL - Plumbing Roof Drains | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
06/10/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 06/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP Drywall.} | |
06/24/2022 | COT - LCBU - Framing | Passed | {Activity date: 06/24/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/10/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 06/08/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/01/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for metal stud framing above the entry storefront } |
|
09/14/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 09/14/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by RSALDAT1 - CODE ECO/UNITS #T1, #T2, #T3, and House Panel} ; {Activity date: 09/02/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - CODE ECO/UNITS #T1, #T2, #T3, and House Panel} | |
09/19/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
09/19/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to set meter and energize system*NOTE: Two additional transformers to be added to building during Tenant improvement on separate permit. CLEARANCE: Code: ECO.} |
|
09/19/2022 | COT - LCPL - Plumbing Above Ceiling | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
09/19/2022 | COT - LCBU - Sustainability | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
09/19/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/17/2022; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by NGARCIA3 - Partial. Lighting cans in outside soffit and electrical boxes for lighting on side of building} | |
09/19/2022 | BULD - Electrical Clearance | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE ECO} | |
09/19/2022 | COT - LCPL - Plumbing Final | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
09/19/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 09/19/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/24/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for front portion of demising wall, okay to tape progress areas} | |
10/03/2022 | COT - LCPL - Plumbing Progress | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/03/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/03/2022 | COT - LCEL - Outdoor Lighting | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/03/2022 | COT - LCPL - Plumbing Intermediate | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 06/07/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for copper water supply lines within building} | |
10/03/2022 | COT - LCEL - Electrical Final | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 09/02/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for service panels} | |
10/03/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/03/2022 | COT - LCPL - Sewer | Passed | {Activity date: 10/03/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} | |
10/14/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 10/14/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } | |
10/18/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - } | |
10/18/2022 | COT - LCEL - Construction Power | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - } | |
10/18/2022 | COT - FCON - Alarm - Final | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } ; {Activity date: 10/14/2022; Status: Denied; Inspector: CGates; Comment: Entered by CGATES1 - Fire alarm did not transmit signals.} | |
10/18/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: CGates; Comment: Entered by CGATES1 - } ; {Activity date: 10/14/2022; Status: Denied; Inspector: CGates; Comment: Entered by CGATES1 - Fire alarm did not transmit signals.} | |
10/19/2022 | COT - LCBU - Building Final | Passed | {Activity date: 10/19/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - APPROVED, pending special inspections and reports required} ; {Activity date: 10/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by KROBLES1 - } ; {Activity date: 10/03/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - PARTIAL, pending Fire, and all Reports and Conditions are satisfied} | |
12/02/2022 | ENGR Engineering Final | Passed |