Inspection Status: Passed
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 04/26/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Approved |
Entered by NGARCIA3 - Approved for the 5th lift (top of wall) for the 3 masonry walls |
| 04/25/2022 |
COT - LCBU - Masonry Pregrout |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, N,S,W CMU walls for shop 16 topped out and ok to grout. |
| 04/21/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - 4th lift (20’) for the 3 masonry walls |
| 04/14/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - 3rd lift (15’) for the 3 masonry walls |
| 04/12/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - 2nd lift (10’) for the 3 masonry walls |
| 04/08/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial - 1st lift for the 3 masonry walls |
| 04/05/2022 |
COT - LCBU - Masonry Pregrout |
TGAUSP |
Partial Approval |
Entered by NGARCIA3 - Partial for stem wall at north, east and west |