Permit: T21CM08893
Permit Details
Status:
Inspections Complete
Type:
Residential Building - One or Two Family
Address:
5331 S MISSIONDALE RD
Address NEW:
5331 S MISSIONDALE RD
Apply Date:
11/15/2021
Applicant:
Description:
T21DV03244 FIRE DAMAGE REPAIRS
Permit Reviews
Permit Number - T21CM08893
Permit Status: Inspections complete
Permit Description: T21DV03244 FIRE DAMAGE REPAIRS
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 11/15/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 12/14/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Inspections Complete
Permit Number: T21CM08893
Permite Description: T21DV03244 FIRE DAMAGE REPAIRS
Total Outstanding Inspections - 10
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSBU - Roof Nailing | N/A | Not Ready | |
| 10/27/2022 | COT - LCBU - Framing | N/A | Not Ready | |
| 10/26/2022 | COT - RSPL - Rough Soil | N/A | Not Ready | |
| 10/27/2022 | RSME - Mechanical Progress | N/A | Not Ready | |
| 10/26/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Not Ready | |
| 05/09/2024 | COT - RSEL - Construction Power | N/A | Not Applicable | |
| 11/29/2023 | COT - RSEL - Electrical Final | N/A | Partial Pass | Partial pending receptacle at kitchen island and left of cook top. Add receptacle 2' to the right of cooktop. 11/29/2023 |
| 11/29/2023 | COT - RSME - Mechanical Final | N/A | Partial Pass | Secure whips off the roof at gas pack. 11/29/2023 |
| 11/29/2023 | COT - RSPL - Plumbing Final | N/A | Partial Pass | Partial pending hammer arrestor at dish washer and laundry room. 11/29/2023 |
| 11/29/2023 | RSBU - Building Final | N/A | Partial Pass | PARTIAL PENDING OTHER INSPECTIONS. 11/29/2023 |
Completed Inspections
Permit Status: Inspections Complete
Permit Number: T21CM08893
Permit Description: T21DV03244 FIRE DAMAGE REPAIRS
Total Completed Inspections - 10
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSEL - Electrical Underground | Passed | ||
| 09/28/2023 | COT - BULD - SWG Clearance | Passed | Verbal clearance for Southwest Gas. 9/28/2023 | |
| 09/28/2023 | COT - RSPL - Gas Pressure Test | Passed | ||
| 05/09/2024 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | ||
| 05/09/2024 | COT - RSBU - Preslab | Passed | ||
| 05/09/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | ||
| 10/02/2024 | COT - RSEL - Electrical Final | Passed | All corrections were made. Approved. 10/2/2024 | |
| 10/02/2024 | COT - RSME - Mechanical Final | Passed | All corrections were made. Approved. 10/2/2024 | |
| 10/02/2024 | COT - RSPL - Plumbing Final | Passed | All corrections were made. Approved. 10/2/2024 | |
| 10/02/2024 | RSBU - Building Final | Passed | All corrections were made. Approved. 10/2/2024 |