Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM08808
Permit Details
Apply Date:
11/09/2021
Applicant:
Ian Regan
Description:
Office Tenant Improvement
Permit Reviews
Permit Number - T21CM08808
Permit Status: Complete
Permit Description: Office Tenant Improvement
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
11/09/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 11/23/2021 | COMPLETED |
12/06/2021 | RESUBMITTAL | 12/07/2021 | COMPLETED |
03/15/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/20/2023 | APPROVED |
Conditions
Permit Number - T21CM08808
Permit Status: Complete
Permit Description: Office Tenant Improvement
Date | Description | Comments |
---|---|---|
09/01/2022 | Air Balance Report Required |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM08808
Permite Description: Office Tenant Improvement
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/12/2022 | COT - LCEL - Electrical Underground | N/A | Canceled | {Activity date: 04/12/2022; Status: Not Applicable; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Not Applicable.} |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM08808
Permit Description: Office Tenant Improvement
Total Completed Inspections - 16
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/25/2022 | COT - LCBU - Framing | Passed | {Activity date: 01/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, team rooms and conference rooms complete. Ok to proceed with Sheetrock.} ; {Activity date: 01/20/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, rescheduled for 1/21, see previous notes.} ; {Activity date: 12/21/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Interior frame, fir out, and masonry infill locations in Area (C,D,G,H) ok to insulate and Sheetrock. } |
|
03/18/2022 | COT - HCBU - Interior Shear Bracing | Passed | {Activity date: 03/18/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} | |
03/25/2022 | COT - LCEL - Electrical Intermediate | Passed | {Activity date: 03/25/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved, installation of new Service Entrance Disconnects for existing bus ducts ok to re energize.} | |
04/12/2022 | COT - LCBU - Building Above Ceiling | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, inspection from grid lines (A-E. 1-5) ok to proceed with progress.} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Area C & F above ceiling ok to start dropping ceiling tiles.} ; {Activity date: 01/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - PARTIAL, AREA A-B mechanical ducts ok to insulate and wrap. } |
|
04/12/2022 | COT - LCEL - Electrical Progress | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, above ceiling electrical for west open office areas and top secret offices ok to proceed} ; {Activity date: 03/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, continued progress for corridors and open office areas ok to proceed.} ; {Activity date: 03/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, inspection from grid lines (A-E. 1-5) ok to proceed with progress.} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Area C & F above ceiling ok to start dropping ceiling tiles. Note: secure MC within 12” of boxes and where exceeds 6’. Inspection for feeders and interconnection to Bus duct required.} | |
04/12/2022 | COT - LCME - Mechanical Above Ceiling | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/12/2022 | COT - LCME - Mechanical Progress | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, continued progress for corridors and open office areas ok to proceed.} ; {Activity date: 03/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, inspection from grid lines (A-E. 1-5) ok to proceed with progress.} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Area C & F above ceiling ok to start dropping ceiling tiles. Note: ensure all flex ducts are dropped in designated areas, inspection for register installation and seismic connections required. } |
|
04/12/2022 | COT - LCEL - Electrical Above Ceiling | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/12/2022 | COT - LCME - Mechanical Intermediate | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
04/12/2022 | COT - LCBU - Building Progress | Passed | {Activity date: 04/12/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/18/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, continued progress for corridors and open office areas ok to proceed.} ; {Activity date: 03/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, inspection from grid lines (A-E. 1-5) ok to proceed with progress.} ; {Activity date: 02/09/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Area C & F above ceiling ok to start dropping ceiling tiles.} ; {Activity date: 12/21/2021; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, Above ceiling frame for areas (C,D,G,H) ok to proceed. } |
|
06/30/2022 | COT - LCME - Mechanical Final | Passed | {Activity date: 06/30/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 12/07/2021; Status: Prior to Final Inspectn; Inspector: Pcamare1; Comment: Entered by PCAMARE1 - Air Balance Report required prior to Final Inspection} | |
06/30/2022 | COT - FCON - Sprinkler - Final | Passed | {Activity date: 06/30/2022; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 05/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 05/17/2022; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - } | |
07/27/2022 | COT - FCON - Alarm - Final | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 06/30/2022; Status: Denied; Inspector: jfordney; Comment: Entered by JFORDNE1 - need hornstrobes in soundproof rooms.} ; {Activity date: 05/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 05/17/2022; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - } | |
07/27/2022 | COT - FCON - Fire - Final | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: jfordney; Comment: Entered by JFORDNE1 - } ; {Activity date: 06/30/2022; Status: Denied; Inspector: jfordney; Comment: Entered by JFORDNE1 - alarm must be approved} ; {Activity date: 05/19/2022; Status: Cancelled; Inspector: IVR USER; Comment: Entered by IVR USER - IVRS - RI canceled} ; {Activity date: 05/17/2022; Status: Cancelled; Inspector: jfordney; Comment: Entered by JFORDNE1 - } | |
03/03/2023 | COT - LCBU - Building Final | Passed | ||
03/09/2023 | COT - LCEL - Electrical Final | Passed | pass |