Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Residential Building - One or Two Family
Apply Date:
10/29/2021
Applicant:
Andrea Flood
Description:
SFR F40J19 T19-M0035

Outstanding Activity Conditions

Permit Number - T21CM08533
Permit Status: Issued
Permit Description: SFR F40J19 T19-M0035
Total Outstanding Activity Conditions - 1
Date Name
11/12/2021 ISSUED WITH PCRWRD CONDITIONS:NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD

Outstanding Inspections

Permit Status: Issued
Permit Number: T21CM08533
Permite Description: SFR F40J19 T19-M0035
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/08/2022 COT - RSME - Mechanical Final N/A Re-inspection required correctly insulate line sets

Completed Inspections

Permit Status: Issued
Permit Number: T21CM08533
Permit Description: SFR F40J19 T19-M0035
Total Completed Inspections - 22
Date Description Inspector Results Comments
01/07/2022 COT - RSPL - Yard Water Line Passed {Activity date: 01/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
01/07/2022 COT - RSPL - Sewer Passed {Activity date: 01/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
01/07/2022 COT - RSPL - Rough Soil Passed {Activity date: 01/07/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP}
01/20/2022 COT - RSEL - Grounding/Bonding Passed {Activity date: 01/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
01/20/2022 COT - RSBU - Preslab Passed {Activity date: 01/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
01/20/2022 COT - RSEL - Electrical Underground Passed {Activity date: 01/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
01/20/2022 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 01/20/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved}
03/01/2022 COT - RSBU - Roof Nailing Passed {Activity date: 03/01/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved}
03/02/2022 COT - RSBU - Exterior Clips/Sheathing Passed {Activity date: 03/02/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Partial approval 13 sheer wall nailing pattern at second story not correct back, one header on first floor missing nail strap, no backing for stair rails}
07/29/2022 COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. Passed {Activity date: 07/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/27/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE
1. Incorrect lags used in stud shoes, incorrect size of stud shoe
2. Gas pressure test fail
3. Anchor bolts required within 12” of end of plate
4. Block under staid landing at floor joint
5. Insulate behind tub
6.maintain 10’ clearance between vent and fresh air intake
7. Repair abandoned fresh air hole in roof}
07/29/2022 COT - LCBU - Framing Passed {Activity date: 07/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/27/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE}
07/29/2022 COT - LCPL - Plumbing Intermediate Passed {Activity date: 07/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/27/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE}
07/29/2022 RSME - Mechanical Progress Passed {Activity date: 07/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/27/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE}
07/29/2022 COT - RSPL - Gas Pressure Test Passed {Activity date: 07/29/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 07/27/2022; Status: Denied; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - DE}
08/12/2022 COT - HCBU - Interior Shear Bracing Passed {Activity date: 08/12/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP}
10/03/2022 PDSD Building Division - TEP PM Clearance Passed {Activity date: 10/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - CODE ECO}
10/03/2022 COT - RSEL - Construction Power Passed {Activity date: 10/03/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by VVERA1 - AP
TEP ECO}
10/18/2022 COT - RSPL - Plumbing Final Passed {Activity date: 10/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - AP
SWG clearance required} ; {Activity date: 11/12/2021; Status: Prior to Final Inspectn; Inspector: AHOLLIS; Comment: Entered by AHOLLIS1 - ISSUED WITH PCRWRD CONDITIONS:

NO FINAL UNTIL THE PUBLIC SEWER G-2020-052 IS ACCEPTED AND RELEASED BY PCRWRD}
10/18/2022 COT - BULD - SWG Clearance Passed {Activity date: 10/18/2022; Status: Approved; Inspector: TLUNDBERG; Comment: Entered by NGARCIA3 - CODE GAS}
10/26/2022 FCON – OH Piping & Hydro Passed
11/08/2022 RSBU - Building Final Passed
11/08/2022 COT - RSEL - Electrical Final Passed

Documents

File Name Document Type  
1_APPLICATION.PDF DOCUMENTS VIEW
1_SITEPLAN.PDF DOCUMENTS VIEW
1_SPECIAL_INSPECTION.PDF DOCUMENTS VIEW
JOB CARD.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW