Permit: T21CM08421
Permit Details
Status:
Complete
Type:
Commercial Building
Address:
3686 E SPEEDWAY BL
Address NEW:
3686 E SPEEDWAY BL
Apply Date:
10/26/2021
Applicant:
Lisa Bowers
Description:
New Exterior Canopy, Seating Area, Permanent Food Truck/Kitchen
Permit Reviews
Permit Number - T21CM08421
Permit Status: Complete
Permit Description: New Exterior Canopy, Seating Area, Permanent Food Truck/Kitchen
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/14/2022 | RESUBMITTAL | 10/20/2022 | ACTIVE |
| 10/26/2021 | 3RD PARTY REVIEW - COMMERCIAL TI | 09/22/2022 | COMPLETED |
| 12/06/2022 | COMMERCIAL REVIEW - FULL v.1 | 01/17/2023 | APPROVED |
| 11/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 11/21/2023 | APPROVED |
| 11/13/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 11/14/2023 | REQUIRES RESUBMIT |
| 10/28/2022 | COMMERCIAL REVIEW - FULL v.1 | 11/17/2022 | APPROVED |
Conditions
Permit Number - T21CM08421
Permit Status: Complete
Permit Description: New Exterior Canopy, Seating Area, Permanent Food Truck/Kitchen
| Date | Description | Comments |
|---|---|---|
| 09/22/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 09/22/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 09/22/2022 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. | |
| 09/22/2022 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. | |
| 09/22/2022 | SPECIAL INSPECTION IS REQUIRED - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION. | |
| 05/15/2023 | Contractor's active Arizona Contractor's License number for specified scope of work required prior to issuance of permit. | |
| 11/21/2023 | SPECIAL INSPECTION FOR SPECIAL GRADING, EXCAVATION AND FILLING IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM08421
Permite Description: New Exterior Canopy, Seating Area, Permanent Food Truck/Kitchen
Total Outstanding Inspections - 3
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/22/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | {Activity date: 09/22/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
| 07/27/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | |
| COT - FCON - Fire - Final | N/A | Not Ready | Need to test ansul system in trailer before final can be given |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM08421
Permit Description: New Exterior Canopy, Seating Area, Permanent Food Truck/Kitchen
Total Completed Inspections - 15
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/18/2023 | COT - HCPL - Rough Soil | Passed | Approved. Okay to backfill. Shading is required. 5/18/2023 Checked the grease interceptor as well. Under test. |
|
| 05/18/2023 | COT - HCEL - Electrical Underground | Passed | Approved. Okay to backfill.5/18/2023 | |
| 05/18/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
| 06/14/2023 | COT - HCBU - Stem Wall/Retaining Wall | Passed | Rebar reinforcement is in place for retaining walls. Okay to pour concrete. | |
| 07/28/2023 | COT - HCBU - Masonry Pregrout | Passed | 7/28/23: top out/bond beam lift for CMU wall on north side of cookers. | |
| 08/30/2023 | BULD - Electrical Clearance | Passed | TEP INCR 1200A 3PH 4W. panel L-4 | |
| 10/25/2023 | COT - HCEL - Electrical Final | Passed | Metal canopy and fencing are complete. Mechanical, electrical, and plumbing are complete for food preparation trailer and smokers. | |
| 10/25/2023 | COT - HCME - Mechanical Final | Passed | Metal canopy and fencing are complete. Mechanical, electrical, and plumbing are complete for food preparation trailer and smokers. | |
| 10/25/2023 | COT - HCPL - Plumbing Final | Passed | Metal canopy and fencing are complete. Mechanical, electrical, and plumbing are complete for food preparation trailer and smokers. | |
| 10/25/2023 | COT - BULD - SWG Clearance | Passed | Gas line is holding air pressure. Okay to connect meter. | |
| 10/25/2023 | COT - HCBU - Building Final | Passed | Metal canopy and fencing are complete. Mechanical, electrical, and plumbing are complete for food preparation trailer and smokers. | |
| 11/08/2023 | COT - FCON - Alarm - Final | Passed | ||
| 11/08/2023 | COT - FCON - Fire - Final | Passed | ||
| 11/08/2023 | COT - FCON - Hood System - Final | Passed | ||
| 11/09/2023 | FCON – Fire – Intermediate | Passed |