Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/14/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 4-14-24: Caissons. | |
| 06/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 4-14-24: Caissons. 6/1/23: reinforcing at trailer pad approved at risk, pending a clear print of matt bar size. Footing at north CMU wall approved |
|
| 06/13/2023 | COT - HCBU - Excavation/Rebar/Zoning | Re-inspection required | 4-14-24: Caissons. 6/1/23: reinforcing at trailer pad approved at risk, pending a clear print of matt bar size. Footing at north CMU wall approved 6/13/23: reinforcing for retaining wall not per plan. |
|
| 07/05/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 4-14-24: Caissons. 6/1/23: reinforcing at trailer pad approved at risk, pending a clear print of matt bar size. Footing at north CMU wall approved 6/13/23: reinforcing for retaining wall not per plan. 7/5/23: reinforcing at exterior dining pad approved. |
|
| 07/27/2023 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass |