Permit: T21CM08092
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
1003 N CONTZEN AV
Address NEW:
1003 N CONTZEN AV
Apply Date:
10/12/2021
Applicant:
Description:
NEW SFR SWC1320 T19-M0080
Permit Reviews
Permit Number - T21CM08092
Permit Status: Issued
Permit Description: NEW SFR SWC1320 T19-M0080
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/10/2022 | RESUBMITTAL | 01/11/2022 | COMPLETED |
| 10/12/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 11/04/2021 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T21CM08092
Permit Status: Issued
Permit Description: NEW SFR SWC1320 T19-M0080
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/11/2022 | This building permit approval is without public sewer connection review or approval. It is strictly the responsibility of the owner and/or person doing the work to ensure that the appropriate review and approval to connect is obtained from Regional Wastewater Reclamation Department (RWRD) wastewater provider or Pima County DEQ approval of/and alternative disposal system. It is required that owner and/or person doing the work solicit all requisite approvals from the wastewater provider prior to obtaining this building construction permit. RWRD connection information is available at www.pima.gov/wwm/developer.htm |
| 01/11/2022 | PIMA COUNTY WASTEWATER SIGN OFF REQUIRED PRIOR TO ISSUANCE OF FINAL STATUS. |
| 10/12/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 10/12/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM08092
Permite Description: NEW SFR SWC1320 T19-M0080
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - RSPL - Yard Water Line | N/A | Not Ready | |
| 10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM08092
Permit Description: NEW SFR SWC1320 T19-M0080
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 01/24/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover progress areas.} | |
| 01/26/2022 | COT - RSBU - Preslab | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to place concrete in footings and on slab. Ensure slab is termite treated.} | |
| 01/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 01/26/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
| 02/15/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to dry in roof system.} | |
| 02/15/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 02/15/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok to cover exterior walls.} | |
| 02/18/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/18/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
| 04/01/2022 | PDSD Building Division - TEP PM Clearance | Passed | {Activity date: 04/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - CODE TMPP} | |
| 04/01/2022 | COT - RSEL - Construction Power | Passed | {Activity date: 04/01/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved. Ok for temporary power. CLEARANCE: Code: TMPP} |
|
| 10/18/2022 | COT - RSPL - Sewer | Passed | {Activity date: 10/18/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved saddle connection to main} ; {Activity date: 09/09/2022; Status: Cancelled; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Inspection canceled by contractor} | |
| 12/22/2022 | COT - LCPL - Plumbing Intermediate | Passed | ||
| 12/22/2022 | COT - RSME - Mechanical Final | Passed | ||
| 12/22/2022 | COT - LCBU - Framing | Passed | ||
| 12/22/2022 | RSME - Mechanical Progress | Passed | ||
| 12/22/2022 | RSBU - Building Final | Passed | ||
| 12/22/2022 | COT - RSEL - Grounding/Bonding | Passed | ||
| 12/22/2022 | COT - RSEL - Electrical Final | Passed | ||
| 12/22/2022 | COT - RSEL - Outdoor Lighting | Passed | ||
| 12/22/2022 | COT - RSPL - Plumbing Final | Passed |