Permit: T21CM07134
Permit Details
Apply Date:
09/02/2021
Applicant:
Ashley Scholz
Description:
Health Center
Architects:
- Tammy George- Moody Nolan
Contractors:
- Rob Hefley
Permit Reviews
Permit Number - T21CM07134
Permit Status: C of o
Permit Description: Health Center
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
09/02/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 09/29/2021 | COMPLETED |
10/12/2021 | RESUBMITTAL | 10/27/2021 | COMPLETED |
11/10/2021 | RESUBMITTAL | 11/22/2021 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T21CM07134
Permit Description: Health Center
Total Completed Inspections - 32
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/22/2021 | PLUMBING - FINAL | PCAMARE1 | Approved | Water Chlorination Report required prior to Final Inspection |
11/22/2021 | MECHANICAL - FINAL | PCAMARE1 | Approved | Air Balance Report required prior to Final Inspection |
12/02/2021 | ELECTRIC - UNDERGROUND | ESTEVENS | Approved | Approved. |
12/02/2021 | PLUMBING - ROUGH, SOIL | ESTEVENS | Approved | Approved. |
12/07/2021 | SHEET ROCK NAILING | DQUINN | Approved | Pa South demising wall, double sided, ok to tape. |
12/07/2021 | PLUMBING - PRE SLAB | DQUINN | Approved | Ap All concrete cuts ok to pour back. |
12/23/2021 | PLUMBING - INTERMEDIATE | DQUINN | Approved | pa In-wall plumb, elec and frame ok in rooms - 147 120 121 148 150 136 137 103 104 116 119 125 |
12/23/2021 | ELECTRIC - INTERMEDIATE | DQUINN | Approved | pa |
12/23/2021 | FRAMING | DQUINN | Approved | pa |
01/11/2022 | PLUMBING - ABOVE CEILING | ESTEVENS | Approved | . Approved |
02/07/2022 | MECHANICAL - ABOVE CEILING | ESTEVENS | Approved | Approved |
02/07/2022 | ELECTRIC - ABOVE CEILING | ESTEVENS | Approved | Approved |
02/07/2022 | BUILDING ABOVE CEILING | ESTEVENS | Approved | Approved |
02/09/2022 | TEP CLEARANCE - PM | DQUINN | Approved | CODE INCR |
02/09/2022 | ELECTRIC - FINAL | DQUINN | Approved | Ap Clear incr Close permit |
02/09/2022 | ELECTRIC - SERVICE UPGRADE | DQUINN | Approved | Ap Called TEP at 9:55 |
02/16/2022 | GAS CLEARANCE | DQUINN | Approved | CODE GAS |
02/16/2022 | PLUMBING - GAS PRESSURE TEST | DQUINN | Approved | Ap Welded gas line to roof for heaters ok. Clear gas. |
05/06/2022 | MECHANICAL - INTERMEDIATE | WGALLAGHER | Approved | Approved please install strong back on capped curb so as to not allow standing water |
05/19/2022 | FIRE SPKLR - FINAL | wmotto | Approved | |
05/19/2022 | FIRE - ALARM FINAL | wmotto | Approved | |
05/19/2022 | ELECTRIC - OUTDOOR LIGHTING | DQUINN | Approved | na |
05/19/2022 | ELECTRIC - PROGRESS | DQUINN | Approved | Ap |
05/19/2022 | BUILDING - PROGRESS | DQUINN | Approved | Ap |
05/19/2022 | FIREWALL/FIREBARRIER/FIRESTOP | DQUINN | Approved | Ap |
05/20/2022 | MECHANICAL - PROGRESS | DQUINN | Approved | Ap |
05/20/2022 | PLUMBING - PROGRESS | DQUINN | Approved | Ap |
05/20/2022 | PLUMBING - BACK WATER VALVE | DQUINN | Approved | na |
05/20/2022 | PLUMBING - SEWER HCS CONNECT | DQUINN | Approved | na |
05/20/2022 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | na |
05/26/2022 | FIRE - FINAL | jfordney | Approved | |
05/27/2022 | BUILDING - FINAL | DQUINN | Approved | Ap Ok for C of O Close permit Please enter these results ASAP. TY |