Permit: T21CM06056
Permit Details
Status:
Issued
Type:
Residential Building - One or Two Family
Address:
5831 E LEE ST
Address NEW:
5831 E LEE ST
Apply Date:
07/26/2021
Applicant:
Description:
Bathroom and Patio Addition
Permit Reviews
Permit Number - T21CM06056
Permit Status: Issued
Permit Description: Bathroom and Patio Addition
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/26/2021 | RESIDENTIAL - BLDG/ZONING/ENGINE/NPPO | 08/24/2021 | COMPLETED |
| 09/07/2021 | RESUBMITTAL | 09/21/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM06056
Permite Description: Bathroom and Patio Addition
Total Outstanding Inspections - 1
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/27/2022 | RSBU - Building Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM06056
Permit Description: Bathroom and Patio Addition
Total Completed Inspections - 12
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/30/2021 | COT - RSBU - Preslab | Passed | {Activity date: 09/30/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1005, 1015. Approved. } |
|
| 09/30/2021 | COT - RSBU - Excavation/Rebar/Zoning | Passed | {Activity date: 09/30/2021; Status: Approved; Inspector: ESTEVENS; Comment: Entered by VVERA1 - 1005, 1015. Approved. } |
|
| 10/11/2021 | COT - BULD - SWG Clearance | Passed | {Activity date: 10/11/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - CODE GAS} | |
| 10/11/2021 | COT - RSPL - Gas Pressure Test | Passed | {Activity date: 10/11/2021; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Approved ok for clearance} | |
| 10/22/2021 | COT - RSPL - Rough Soil | Passed | {Activity date: 10/22/2021; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - -AP} ; {Activity date: 10/11/2021; Status: Not ready for Inspection; Inspector: WGALLAGHER; Comment: Entered by NGARCIA3 - Not ready} | |
| 01/28/2022 | COT - RSBU - Roof Nailing | Passed | {Activity date: 01/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 01/28/2022 | COT - RSBU - Exterior/Interior Clips/Sheathing/Framing | Passed | {Activity date: 01/28/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 02/18/2022 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, HVAC and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | Passed | {Activity date: 02/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 01/28/2022; Status: Partial Approval; Inspector: RCHANDLER; Comment: Entered by VVERA1 - PA. Electric and plumbing only; balance, including clips at patio not ready.} | |
| 02/18/2022 | COT - LCBU - Framing | Passed | {Activity date: 02/18/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - AP} ; {Activity date: 01/28/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by VVERA1 - NR. See 1080 inspection notes. } |
|
| 07/27/2022 | COT - RSME - Mechanical Final | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} | |
| 07/27/2022 | COT - RSPL - Plumbing Final | Passed | {Activity date: 07/27/2022; Status: Approved; Inspector: RCHANDLER; Comment: Entered by VVERA1 - AP} ; {Activity date: 02/18/2022; Status: Not ready for Inspection; Inspector: RCHANDLER; Comment: Entered by NGARCIA3 - -NR Sam wants 10:00 520-869-0442 Field 12-2 Texted ETA at 8:23} |
|
| 11/18/2022 | COT - RSEL - Electrical Final | Passed |