Permit: T21CM05532
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
2945 N BEAR CANYON RD BLDG 11
Address NEW:
2945 N BEAR CANYON RD BLDG 11
Apply Date:
07/06/2021
Applicant:
Jim Morrison
Description:
New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
Permit Reviews
Permit Number - T21CM05532
Permit Status: Inspections
Permit Description: New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2022 | RESUBMITTAL | 03/04/2022 | COMPLETED |
| 07/06/2021 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 08/06/2021 | COMPLETED |
| 08/25/2021 | RESUBMITTAL | 09/28/2021 | COMPLETED |
| 11/01/2021 | RESUBMITTAL | 02/10/2022 | COMPLETED |
| 09/27/2024 | COMMERCIAL REVIEW - FULL v.2 | 10/11/2024 | REQUIRES RESUBMIT |
| 07/23/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 08/13/2025 | APPROVED |
| 07/25/2023 | COMMERCIAL REVIEW - FULL v.1 | 08/21/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T21CM05532
Permit Status: Inspections
Permit Description: New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
Total Outstanding Activity Conditions - 12
| Date | Name |
|---|---|
| 07/23/2025 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 07/23/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 07/23/2025 | ??? Designs must be submitted and approved prior to ... |
| 07/23/2025 | SPECIAL INSPECTION FOR POST TENSION SLAB IS REQUIRED. |
| 07/23/2025 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. |
| 07/23/2025 | Separate TFD permits are required for: Fire Alarm System |
| 07/23/2025 | Separate TFD permits are required for: Fire Sprinkler System |
| 07/23/2025 | SPECIAL INSPECTION FOR SHOTCRETE IS REQUIRED. |
| 07/23/2025 | Stair Designs must be submitted and approved prior to... |
| 07/23/2025 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 07/23/2025 | Truss/Joist Design plans must be submitted and approved prior to intermediate inspections if residential building or finaling the permit if commercial building. |
| 07/23/2025 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Conditions
Permit Number - T21CM05532
Permit Status: Inspections
Permit Description: New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
| Date | Description | Comments |
|---|---|---|
| 02/18/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: T21CM05532
Permite Description: New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
Total Outstanding Inspections - 39
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/04/2022 | COT - LCBU - Building Above Ceiling | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Electrical Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Building Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Electrical Intermediate | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Framing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Electrical Underground | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCME - Mechanical Above Ceiling | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCME - Mechanical Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Excavation/Rebar/Zoning | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Firewall/Fire Barrier/Firestop | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Roof Drains | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Outdoor Lighting | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Preslab | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | PDSD Site/Engineering Division - NPPO | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Intermediate | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | TRSP - ROW - Final/Close-Out | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Alarm - Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Electrical Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | ENGR Engineering Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Sprinkler - Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Exterior Clips/Sheathing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Plumbing Above Ceiling | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Sustainability | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Rough Soil | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - FCON - Fire - Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCEL - Electrical Above Ceiling | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | PDSD Building Division - Sign Final | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCME - Mechanical Intermediate | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Roof Nailing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCBU - Building Progress | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Sewer | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - HCBU - Interior Shear Bracing | N/A | Canceled | Inspection Canceled |
| 11/04/2022 | COT - LCPL - Backwater Valve | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | COT - LCME - Mechanical Final | N/A | Canceled | Inspection Canceled |
| 11/07/2022 | COT - LCPL - Plumbing Final | N/A | Canceled | Inspection Canceled |
| 11/06/2025 | FCON – Fire – Intermediate | N/A | Partial Pass | stub out approved. |
Completed Inspections
Permit Status: Inspections
Permit Number: T21CM05532
Permit Description: New 256 unit apartment complex. There are 18 buildings. Each bldg assigned separate permit. Bldg 1 -
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/25/2025 | COT - HCPL - Rough Soil | Passed |