Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T21CM05003
Permit Details
Apply Date:
06/15/2021
Applicant:
JR Durazo
Description:
New Townhome
Permit Reviews
Permit Number - T21CM05003
Permit Status: Issued
Permit Description: New Townhome
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/14/2021 | 3RD PARTY REVIEW - RESIDENTIAL | 08/04/2021 | COMPLETED |
08/19/2021 | RESUBMITTAL | 10/04/2021 | COMPLETED |
04/19/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 04/24/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - T21CM05003
Permit Status: Issued
Permit Description: New Townhome
Total Outstanding Activity Conditions - 5
Date | Name |
---|---|
08/04/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. |
08/04/2021 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR RE-BAR |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR SOILS EXCAVATION |
08/04/2021 | SPECIAL INSPECTION IS REQUIRED FOR MORTAR AND GROUT |
Conditions
Permit Number - T21CM05003
Permit Status: Issued
Permit Description: New Townhome
Date | Description | Comments |
---|---|---|
08/04/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) |
Outstanding Inspections
Permit Status: Issued
Permit Number: T21CM05003
Permite Description: New Townhome
Total Outstanding Inspections - 12
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | COT - RSME - Mechanical Final | N/A | Not Ready | |
10/27/2022 | RSBU - Building Final | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - LCBU - Sustainability | N/A | Not Ready | |
10/27/2022 | COT - RSPL - Plumbing Final | N/A | Not Ready | |
10/26/2022 | COT - RSEL - Construction Power | N/A | Not Ready | |
10/27/2022 | COT - RSEL - Electrical Final | N/A | Not Ready | |
10/26/2022 | COT - RSBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
04/06/2023 | COT - RSEL - Electrical Underground | N/A | Partial Pass | |
09/07/2023 | COT - LCPL - Plumbing Above Ceiling | N/A | Not Applicable | |
08/05/2024 | COT - RSBU - Residential Intermediate may include Framing, Electrical, Plumbing, and/or Mechanical work. Only one inspection may be attached for all trades for final rough-in. | N/A | Partial Pass | This inspection is for South Masonry wall at 22’, topped-out. Ok to grout progress areas. |
09/20/2024 | BULD - Electrical Clearance | N/A | Re-inspection required | 9/20/24: grounds and neutrals must be separated at sub-panels. NFPA 70 . NEC 250.142. |
Completed Inspections
Permit Status: Issued
Permit Number: T21CM05003
Permit Description: New Townhome
Total Completed Inspections - 12
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/22/2022 | COT - RSPL - Rough Soil | Passed | {Activity date: 07/22/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by VVERA1 - Approved} | |
08/17/2022 | COT - RSBU - Preslab | Passed | {Activity date: 08/17/2022; Status: Approved; Inspector: JBURGE; Comment: Entered by NGARCIA3 - Approved. Ok to place concrete in progress areas} | |
02/15/2023 | COT - RSBU - Excavation/Rebar/Zoning | Passed | ||
02/15/2023 | COT - RSEL - Grounding/Bonding | Passed | partial approval for UFER | |
02/15/2023 | COT - RSPL - Sewer | Passed | ||
05/04/2023 | COT - RSPL - Yard Water Line | Passed | ||
07/14/2023 | COT - RSBU - Firewall/Fire Barrier/Firestop | Passed | ||
07/14/2023 | COT - LCBU - Framing | Passed | ||
09/07/2023 | COT - LCPL - Plumbing Intermediate | Passed | ||
09/07/2023 | RSME - Mechanical Progress | Passed | ||
10/05/2023 | RSEL - Electrical Progress | Passed | 10/5/23: Electrical intermediate passed. | |
09/26/2024 | BULD - Electrical Clearance | Passed | Ok to set meter for new service. |